Documented fact
The City of Gilroy says AWS's Phase 1 data center is expected to use approximately 23 acre-feet of potable water per year, falling to an estimated 2 acre-feet per year after a required switch to recycled water.
Said by the City of Gilroy · Gilroy Data Center
Review scope: City of Gilroy project page captured 5 October 2026
Evidence and limits
Evidence limitation: Measured potable or recycled water use after opening; the recycled-water volume; the recycled-water agreements' terms and whether they were completed; the Water Supply Assessment (the page lists it as Appendix O of the environmental review, not read); and the conditions-of-approval text.
Read the answer and sources →Checked 5 October 2026