Public statement checked
Answer
Verdict on the wording above: Company claim as of Google PDF checked 2026-10-01 The only support is the company or its agents. Shown as stated, not adopted. Not a finding that it is true or false. How verdicts work →
- Who stated it
- Said by Google · company statement in Google and Intersect announcement · 4 June 2026 →
- What the evidence establishes
- The announcement states a company commitment that infrastructure-growth costs are not passed to local families. It is not a tariff or a customer-bill finding. Shown as the company's statement, not as a finding either way.
- Biggest limitation
- The tariff, rate, or interconnection agreement that would show who pays. Any later bill or regulator order.
- Checked
- 1 October 2026 · Next review: A tariff, interconnection agreement, or regulator order allocating this project's infrastructure costs
Evidence
What the evidence supports
The PDF says Google pays for 100 percent of the power it uses, will cover the infrastructure needs driven by its growth, and shares a commitment with Intersect that the buildout of energy and data-center infrastructure does not pass the costs of that growth on to local families. That is a company commitment in an announcement. It is not a tariff order, an interconnection agreement, or a finding about other customers' bills. The blog's 'power first' wording does not restate this cost sentence.
Still unknown
The tariff, rate, or interconnection agreement that would show who pays. Any later bill or regulator order.
Sources
-
Google and Intersect announcement, Gray and Roberts Counties → Company
Exact location Section 'Supporting the grid, powering the future': pays for 100 percent of the power it uses; will cover infrastructure needs driven by its growth; commitment that the buildout does not pass infrastructure-growth costs on to local families.
What it supports States the company cost commitment. Not a tariff or a customer-bill record.
Review details
Scope
- Unit
- company infrastructure-cost commitment
- Geography
- Meitner Energy Center infrastructure, Gray and Roberts Counties, Texas
- Period
- stated 2026-06-04; no tariff proceeding identified
- As of
- Google PDF checked 2026-10-01
- Confidence
- medium — Company announcement only. No tariff or rate order reviewed.
- Kind
- Public statement checked
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Chronology
- Stated by Google
- Published — Google and Intersect announcement, Gray and Roberts Counties
- Source retrieved
- Checked by DataCenterData
- Date not established Next review: A tariff, interconnection agreement, or regulator order allocating this project's infrastructure costs
Corrections and history
No corrections or wording changes recorded for this claim.
Data
Suggest a correction
Suggest a correction → Claim ID meitner-infrastructure-cost and this page are prefilled. Accepted material corrections appear publicly on Changes.