Public statement checked
Answer
Verdict on the wording above: Company claim as of Google PDF and blog checked 2026-10-01 The only support is the company or its agents. Shown as stated, not adopted. Not a finding that it is true or false. How verdicts work →
- Who stated it
- Said by Google · company statement in Google and Intersect announcement · 4 June 2026 →
- What the evidence establishes
- Google's 4 June 2026 announcement describes planned wind, solar and battery capacity of more than one gigawatt beside a new data center, with a minority of demand met by on-site gas. The same-day blog states co-located generation and does not state that gigawatt figure. This is not data-center IT load. Shown as the company's statement, not as a finding either way.
- Biggest limitation
- Whether any of that generation is built, energized, or metered. The split of the gigawatt figure among wind, solar, and batteries. The capacity of the on-site gas. Data-center IT load. Hourly matching between generation and the data center.
- Checked
- 1 October 2026 · Next review: A utility, permit, or meter record for this generation, or a stated data-center IT capacity
Evidence
What the evidence supports
The PDF datelined Gray and Roberts Counties, Texas, 4 June 2026, says the Meitner Energy Center includes a data center co-located with more than a gigawatt of wind, solar, and battery storage systems. It says the majority of the site's power will come from clean energy on Day One, with a minority of demand met by on-site gas. The same day's Google blog says the data center is co-located with new energy generation and dedicated clean power, and it does not state a gigawatt figure or on-site gas. Neither page states a data-center IT capacity, an in-service date, or metered output. The PDF's Haskell County Quantum project, described there as 640 MW of solar and 1.3 GWh of storage, is a different site.
Still unknown
Whether any of that generation is built, energized, or metered. The split of the gigawatt figure among wind, solar, and batteries. The capacity of the on-site gas. Data-center IT load. Hourly matching between generation and the data center.
Sources
-
Google and Intersect announcement, Gray and Roberts Counties → Company
Exact location Section 'Supporting the grid, powering the future': a data center co-located with more than a gigawatt of wind, solar, and battery storage; majority clean energy on Day One; minority on-site gas.
What it supports States the gigawatt wind, solar, and storage figure and the minority on-site gas share. Does not state data-center IT capacity or metered output.
-
Google blog: Meitner Energy Center → Company
Exact location Opening paragraphs: construction of the Meitner Energy Center; a data center co-located with new energy generation and dedicated clean power. The blog links to the PDF.
What it supports States co-located generation and dedicated clean power. Does not state a gigawatt figure or on-site gas.
Review details
Scope
- Unit
- planned co-located generation
- Geography
- Meitner Energy Center, Gray and Roberts Counties, Texas
- Period
- announced 2026-06-04; no completion date stated
- As of
- Google PDF and blog checked 2026-10-01
- Confidence
- medium — Company announcement and same-day company blog. No utility, permit, or meter record reviewed.
- Kind
- Public statement checked
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Chronology
- Stated by Google
- Published — Google and Intersect announcement, Gray and Roberts Counties
- Published — Google blog: Meitner Energy Center
- 2 sources retrieved
- Checked by DataCenterData
- Date not established Next review: A utility, permit, or meter record for this generation, or a stated data-center IT capacity
Corrections and history
No corrections or wording changes recorded for this claim.
Data
Suggest a correction
Suggest a correction → Claim ID meitner-gray-roberts-generation and this page are prefilled. Accepted material corrections appear publicly on Changes.