Massachusetts index · last changed 14 September 2026

Massachusetts data centers: what the public record shows.

Selected source-linked records are published below. This is not a complete inventory of Massachusetts data centers.

7 sourced policy records for Massachusetts ↓Facility register: 32 records · by county →1 published DataCenterData record · evidence status shown per row23 licensed directory leads · not independently verifiedThese counts overlap and are not added together

Explore Massachusetts

Map, listings and checked facts.

Start with 23 licensed source leads, then inspect the separate public-evidence layer below. Licensed rows are not independently verified and are not a statewide census.

Massachusetts map

Reported locations in Massachusetts

23 licensed rows · 18 source localities · 2 map targets

Open interactive map
Source-reported points; some are approximate. Not parcel boundaries. Exact Approximate or representative Bounded nearby groupA number on a marker is the count of licensed rows it holds.Licensed layer only (Compute Atlas, source data through 14 October 2026). The interactive map lists 42 data-center source listings here across licensed, operator and DataCenterData layers (29 with a map point); 44 with government registry records. Source listings are not distinct sites.
Browse 2 mapped areas as links
Map sources and method

The state outline is adapted from the U.S. Census Bureau 2025 cartographic boundary file. Facility coordinates are adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Outline and markers use one geographic projection before any explicitly disclosed readability offset. Exact singleton source anchors are never moved. A one-kilometre boundary tolerance prevents the simplified 1:20,000,000 outline from hiding legitimate border-area source points; farther conflicts are disclosed, not clamped. DataCenterData groups source-reported city coordinates only within a bounded map radius; the outline does not validate a facility record. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

23 licensed rows18 reported city labels19 eligible organization labels

Browse all 23 rows below. Licensed rows are not independently verified and remain separate from the checked public-evidence layer.

  1. source-reported operationalReported operational 2.8 MWSource updated 6 October 2026approximate location
  2. source-reported proposedCapacity not statedSource updated 6 October 2026approximate location

Separate layer

Also listed by operators

Sites that operators list on their own websites and that are not rows in the licensed directory above. They are kept apart and never added to the licensed rows.

7 operator-listed sites (mixed units; not added to licensed rows) in Massachusetts →

2 of these sites have no supported coordinate. The map does not invent a pin or a metro placement for them.

Massachusetts evidence at a glance

A few checked sites

Selected public evidence, not a statewide census. Each row shows whether it is independently source-linked, attributed, or unresolved; licensed leads remain separate.

Published project / campus
0
Published facility / building
1
Attributed or unresolved rows
0
Licensed directory leads
23 not independently verified
Capacity boundary stated
0 of 1 published DataCenterData rows
Review timing
Audit through 12 September 2026 · next 13 March 2027
Known coverage gap

www.mass.gov is unreachable in the current review, so no state incentive programme page, award list or certification register was read.

Browse all 23 Massachusetts licensed leads → · Why these counts differ →

Buildings

1 building record. Names are as they appear on each record page.

Buildings published for Massachusetts
Record / rolesStatusCapacity / scalePrimary evidence
Massachusetts Green High Performance Computing CenterOwner: Massachusetts Green High Performance Computing operatingbuilding · UMass Amherst service report dated 2026-04-19 UnknownNo independently supported figureNo capacity is published from the selected records. The intake's 15 MW value is not carried because its precise critical-IT, gross-facility, design, or current-load scope was not established from these sources. MassGIS Standardized Parcels with Assessor Data — parcel 020-02-003 →Gov. record

Where the records were checked

Statewide audit pending

A few checked sites

This is not a list of every data center in the state, and the number here is not a count of them. There are almost certainly more.

Statewide coverage is not complete. The records below are sourced; a full statewide count has not been published.

State research audit window ended 12 September 2026. Individual records and claims below show their own evidence dates and may be newer.

Next scheduled coverage review: 13 March 2027.

0 independently source-linked project/campus records; 1 independently source-linked facility/building record; 0 attributed or unresolved rows. These counts use different units and must not be added together.

Source families checked, selected records and remaining gaps

These notes name selected records, say which kinds of public evidence were checked and show what remains missing. They do not add anything to the published counts.

  • Economic development incentives — Partly checked
    • www.mass.gov is unreachable in the current review, so no state incentive programme page, award list or certification register was read.
    • The 2024 tax exemption the Compute Atlas notes attribute to the Westfield project was not verified from any source.
    • No Massachusetts Economic Assistance Coordinating Council certified-project list was consulted.
  • Utility commission and large-load records — Checked
    • The docket index carries descriptions and petitioners but not filing text, so a data center named inside a filing rather than in a docket caption would not be found.
    • ISO New England interconnection or large-load queue records were not consulted.
    • Eversource, National Grid and Unitil tariff filings were not read individually.

    Selected records

  • Environmental and construction permits — Partly checked
    • No MassDEP air or emergency-engine permit was read, although the TierPoint Andover page itself describes two 2.5 MW generators that would normally appear in such records.
    • No MEPA Environmental Notification Form or EEA number was retrieved for the Westfield project or any other.
    • Municipal building and grading permits were not reachable; the Westfield and Lowell city sites did not respond during review.

    Selected records

  • Local planning, assessor and map records — Checked
    • Massachusetts assessor use codes have no data center class, so the parcel screen depended on owner names and known addresses; an operator holding a site through an unrecognised LLC would not be found.
    • Westfield and Lowell city sites did not respond during review, so no planning board decision, zoning case or moratorium text was read for either.
    • Boston and Somerville planning and zoning case files were not consulted.
    • MAP_PAR_ID is null for Lowell rows in the statewide layer, so the Markley Lowell parcels are identified by LOC_ID only.

    Selected records

  • Tax abatements and development agreements — Partly checked
    • The 2024 Westfield tax exemption reported in the licensed dataset was not verified.
    • The disputed Lowell abatement and its job commitments were not read.
    • No state Economic Assistance Coordinating Council or municipal TIF register was consulted.

    Selected records

  • Operator disclosures — Checked
    • Amazon Web Services, Microsoft, Google, Meta, Oracle and Apple location pages were not checked for Massachusetts; none of these operators appears in any source opened here.
    • Markley Group's own site was not yet reviewed directly, so its Boston and Lowell capacity claims come only from the licensed dataset.
    • Iron Mountain and Equinix facility pages were not yet reviewed directly, so the two new parcel research leads have no operator disclosure at all.

    Selected records

  • Open datasets and directories — Checked
    • Directory listings (Data Center Map, Baxtel, datacenters.com, PeeringDB) were not yet reviewed directly; the Baxtel and Data Center Map URLs the dataset cites for Westfield and Markley Boston were not retrieved.
    • No cross-check was made against FracTracker or other trackers.

    Selected records

  • Closures, withdrawals and former names — Checked
    • The reported Westfield council moratorium and the reported Lowell moratorium were not read; both city sites did not respond during review.
    • The Massachusetts lawsuit reported against the Lowell facility was not traced to a court docket.
    • No archived or historical sweep was made for Massachusetts data centers that closed before 2021.

    Selected records

  • News and other discovery — Not checked
    • No news or advocacy source was opened for Massachusetts; the Boston Globe, WBUR, Boston.com, Harvard Crimson, NBC Boston and Working Mass articles the licensed dataset cites were not retrieved.

Local evidence by place

Licensed and operator listings, reviewed records, answers and local policy for each place. Listings overlap and are not added; a place without a line here has no published local evidence.

No local evidence answer, reviewed record or local policy record is published for Andover, Billerica, Cambridge, Chelmsford, Grafton, Lowell, Marlborough, Medford, Needham, Somerville. Their listings above are source listings to investigate. No statewide evidence answer is published for Massachusetts either; statewide rules are under Policy tracker below.

Policy tracker

Massachusetts policy records

7 sourced records are associated with this state context. They are grouped below as current, pending and nonbinding, and history, and each card shows its relevant date. These are not facility counts and do not cover every locality.

Current 1 record

Recorded as in effect on the dataset date. This does not mean every project in a represented state is restricted or approved.

Pending or nonbinding 5 records

Adopted measures with unverified effect, adopted future measures, open proceedings, proposals, drafts and nonbinding context stay separate from current rules.

Legislation introduced (any outcome) · Boston only (local rule)

Boston: proposed council order on a zoning text amendment to prohibit data centers (Docket 2026-1718)

Proposed · City of Boston, Massachusetts · Local

Source document: 14 September 2026

Issuing authority: Boston City Council

A Boston City Council order filed on 14 September 2026 (Docket 2026-1718) concerns a text amendment to the Boston Zoning Code that would prohibit data centers in all zoning districts.

Read the sourced record · Primary source

Permanent restriction or prohibition · Mansfield only (local rule)

Mansfield: zoning bylaw prohibiting data centers outside three districts (Town Meeting Article 23)

Adopted; effective status unverified · Town of Mansfield, Massachusetts · Local

Adopted: 5 May 2026

Issuing authority: Mansfield Town Meeting

At the 5 May 2026 session of the Annual Town Meeting, Mansfield voters passed Article 23 by a two-thirds majority, amending the Zoning Bylaws on data centers.

Read the sourced record · Primary source

Legislation introduced (any outcome)

HD.5404 data center electricity cost petition

Proposed · Massachusetts · State

Source document: 5 December 2025

Issuing authority: Massachusetts General Court

House Docket 5404 is a filed petition, An Act relative to the cost of electricity at large and qualified data centers, that would protect residential and income-eligible distribution customers from data-center-driven rate increases and require department review of data center rates and terms.

Read the sourced record · Primary source

History 1 record

Expired, repealed, vetoed, failed, blocked, superseded and completed measures remain visible without being presented as current.

Legislation introduced (any outcome)

Senate amendment 193 (S.3213) data center clean-energy and water permit conditions (rejected)

Did not pass · Massachusetts · State

Ended: 23 July 2026

Issuing authority: Massachusetts Senate

Senate amendment 193 to the 2026 economic development bill proposed permit conditions for data centers of 20 megawatts or more: 100 per cent new clean energy supply, a phase-out of fossil-fuel backup generation, developer payment for fossil-fuel delivery infrastructure, state water certifications and water plans, and cumulative impact analyses.

Read the sourced record · Primary source

Open the Massachusetts policy comparison

Review dates: the 7 Massachusetts records were last checked 23 September 2026 to 3 November 2026. No scheduled review is overdue as of the tracker date 3 November 2026. No single record, and not this list, establishes complete statewide policy coverage.