Scope
West Virginia legislative rule 145 CSR 20, "Rule to Petition the Department of Commerce for Certification of a Microgrid District or Certification as a High Impact Data Center", governs petitions to the Department of Commerce for those two certifications under W. Va. Code 5B-2-21(a) and 5B-2-21a, including eligibility and petition requirements for high impact data centers and annual reporting by certified microgrid districts. The rule states an effective date of 1 April 2026 and a sunset of 1 August 2031.
- Geographic scope
- West Virginia
- Jurisdiction
- State
- Authority type
- Government agency
- Issuing authority
- West Virginia Department of Commerce (Department of Economic Development)
Dates
- Adopted
- 1 April 2026
- Effective
- 1 April 2026
- Scheduled expiration
- 1 August 2031
- Ended
- Not recorded as ended
- Completion condition
- Section 1.5 says the rule terminates and has no further force or effect on 1 August 2031.
- Source document
- 1 April 2026
- Last checked
- 23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)
Summary
West Virginia legislative rule 145 CSR 20 sets out how a petitioner applies to the Department of Commerce for certification of a microgrid district or certification as a high impact data center under the 2025 House Bill 2014 program. The final filing with the Secretary of State states the rule was authorized by House Bill 4983, was filed on 1 April 2026, took effect on 1 April 2026 and terminates on 1 August 2031. It sets eligibility and petition contents; it does not itself certify any project.
What this does not establish
- An emergency version of the rule effective 22 December 2025 is listed on the Secretary of State rule page; it is not recorded separately.
- The rule governs petitions and reporting; the tax and local-preemption consequences of certification come from the statute, not from this rule.
- The list of certified projects was not opened.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement HB 2014: certified microgrid and high impact data center program; local preemption (In effect)
- Related, not a replacement HB 4983 (2026) authorizes the 145 CSR 20 certification rule (In effect)
Sources
https://apps.sos.wv.gov/adlaw/csr/readfile.aspx?DocId=58817&Format=PDF
- West Virginia Secretary of State rule detail, 145-20 Rule history: final file effective 1 April 2026; emergency rule effective 22 December 2025 · 1 April 2026