Summary
Pennsylvania's Department of Environmental Protection published a template consent order and agreement for GRID data center projects under Executive Order 2026-05. The model lists environmental commitments a developer would make, such as Tier 4 or cleaner backup generators, limits on generator runtime, air quality monitors whose data are public, water planning and energy and water best-practice certification. It is a model document; each executed consent order binds only its signatories.
Scope
The Department of Environmental Protection's Template GRID Project Consent Order and Agreement, a model marked Rev. 08/18/2026 that can be changed to fit a project, sets out the commitments a developer of a Computer Data Center makes in a consent order and agreement under Executive Order 2026-05, including backup generation with zero-emission systems or generators with emissions no higher than a Tier 4 or Tier 4 equivalent generator, limits on backup generator use, at least three air quality monitors with public data, a certification of energy and water best management practices, and a written water plan.
- Geographic scope
- Pennsylvania
- Jurisdiction
- State
- Authority type
- Government agency
- Issuing authority
- Pennsylvania Department of Environmental Protection
Dates
- Adopted
- No adoption day is recorded
- Effective
- Not a binding measure
- Scheduled expiration
- No expiration date recorded
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- The source page states no document date
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- This is a model form marked "Rev. 08/18/2026"; bracketed terms are filled in project by project, so an executed order may differ.
- The requirement to enter a consent order comes from Executive Order 2026-05 (record pa-eo-2026-05-data-center-guardrails-20260818), not from this template.
- No executed consent order was opened, and how many developers have signed one was not checked.
- The template is hosted on the Governor's pages of pa.gov; the Department of Environmental Protection is the named party.
Unresolved questions
- How many GRID consent orders have been executed, and with which terms.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement Executive Order 2026-05 data center permitting and incentive conditions (In effect)
Sources
Primary source: Pennsylvania Department of Environmental Protection page on pa.gov