Summary
Sarpy County, Nebraska defines data centers in its zoning regulations and lists them as a principal permitted use in the Heavy General Business and Light Industrial districts and as a special use requiring a permit in the General Business district. The compiled regulations currently posted by the county were approved by Resolution 2024-030 on 23 January 2024.
Scope
The Sarpy County Zoning Regulations, as amended and approved by Resolution 2024-030 on 23 January 2024, define a data center as a centralized repository for the storage, management, processing, conversion and dissemination of data and information, allow data centers in the General Business District (BG) with a special use permit, and list data centers as a principal permitted use in the Heavy General Business District (BGH) and the Light Industrial District (IL).
- Geographic scope
- Sarpy County, Nebraska (county zoning jurisdiction)
- Jurisdiction
- Local
- Authority type
- Local government
- Issuing authority
- Sarpy County Board of Commissioners
Dates
- Adopted
- No adoption day is recorded
- Effective
- Effective date not stated in the source
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The regulations state no expiration.
- Source document
- 23 January 2024
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The date the data center provisions were first adopted was not determined; the same provisions appear in the compilation approved by Resolution 2020-157 on 2 June 2020, so 23 January 2024 is the approval date of the current compilation, not of the provisions.
- The county's zoning jurisdiction boundaries, and any later amendment after Resolution 2024-030, were not checked beyond the county's Regulations page on 2026-09-23.
- City zoning inside Sarpy County (for example Papillion or La Vista) is not covered by this record.
- No effective date is stated in the compiled document; none is stored.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- No related action is recorded.
Sources
Primary source: Sarpy County Board of Commissioners page on sarpy.gov
- Sarpy County Planning and Building, Regulations page — Lists the Resolution 2024-030 complete document as the current zoning regulations
- Sarpy County Zoning Regulations as approved by Resolution 2020-157 (June 2020 compilation) — Shows the data center provisions predate the current compilation · 2 June 2020