Montana-Dakota Utilities service near Center, North Dakota

ND PSC PU-26-235: MDU service agreement for a data center near Center (pending)

Regulatory or tariff proceeding

Pending proceeding This is an open proceeding, not a final rule or tariff approval.

Summary

Montana-Dakota Utilities Co. asked the North Dakota Public Service Commission on 26 June 2026 to approve an electric service agreement with APLD BIS-01 LLC for a high-density data center near Center, North Dakota. A neighboring electric cooperative has protested and requested a hearing. The case was open on 1 October 2026 with no decision on the agreement.

Scope

North Dakota Public Service Commission Case PU-26-235, filed 26 June 2026, concerns Montana-Dakota Utilities Co.'s application for approval of an electric service agreement with APLD BIS-01 LLC. MDU's filing says the agreement provides for the sale of all electric power required by the data center to be located near its Coyote to Center 345 kV transmission line near Center, North Dakota. The case page opened on 23 September 2026 lists a notice of opportunity for hearing, a protest and request for hearing by Roughrider Electric Cooperative (4 September 2026) and an order on protection of information (9 September 2026), and no decision on the agreement.

Geographic scope
Montana-Dakota Utilities service near Center, North Dakota
Jurisdiction
State
Authority type
Regulator or commission
Issuing authority
North Dakota Public Service Commission

Dates

Adopted
No adoption day is recorded
Effective
Not in effect (open proceeding)
Scheduled expiration
No expiration date recorded
Ended
Not recorded as ended
Completion condition
None stated
Source document
26 June 2026
Last checked
3 November 2026
About this date

This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.

What this does not establish

  • This is an open proceeding on a utility application, not a Commission approval; any order will be its own record.
  • Pricing and other terms are redacted in the public filing and are not restated.
  • Related temporary-authority cases for construction load and a switch yard at the same project (PU-26-219, PU-26-236) are certificate cases and are not part of this record.

Unresolved questions

  • Whether the Commission will hold a hearing on the cooperative's protest and whether it will approve the agreement.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.

Sources

Primary source: North Dakota Public Service Commission page on psc.nd.gov

Back to the policy tracker · North Dakota policy module