In plain English
Who it affects: This rate is for data center-type facilities with high density computer processing, in the North Dakota communities Montana-Dakota Utilities serves. A customer must expect at least 10,000 Kw (kilowatts) a month at a single delivery point and a minimum load factor, a measure of how steadily power is used, of 85%.
What it changes: The schedule prints no price. Billing follows each customer's service agreement, approved by the North Dakota Public Service Commission, plus any and all added costs of serving it each month. A customer that does not interrupt when asked pays the greater of $10.00 per Kw of its agreed demand or its share of grid-operator penalties.
Easy to misread: Falling short of the requirements does not by itself end service: the customer is moved to the otherwise applicable rate.
- Minimum expected demand: 10,000 Kw per month, metered at a single delivery point (Original Sheet No. 30)
- Minimum expected load factor: 85% (Original Sheet No. 30)
- Interruption: Up to 200 hours annually, or as included in the electric service agreement (Original Sheet No. 30)
- Service agreement length: Minimum of three years, not more than five years (Original Sheet No. 30)
- Penalty for not interrupting: The greater of $10.00 per Kw of the demand specified in the agreement, or the appropriate reallocation of penalties imposed on the company by the grid operator MISO (Original Sheet No. 30.1)
- Repeat failure: After a second failure within a 12-month period, the customer owes the penalty and may be moved to the otherwise applicable rate (Original Sheet No. 30.1)
Written from Montana-Dakota Utilities North Dakota Electric Rate Schedule, Rate 45 (Original Sheets 30 to 30.2), read on 3 November 2026. A reading aid, not legal advice. The document controls.
Summary
Montana-Dakota Utilities offers North Dakota Rate 45 for data center-type facilities housing high density computer processing technology that expect at least 10,000 kW of monthly demand and an 85 percent load factor. Service is interruptible for up to 200 hours a year, requires a three-to-five-year electric service agreement approved by the Public Service Commission, and bills the customer the incremental costs of service. The current sheets state service rendered on and after 1 July 2023.
Scope
Montana-Dakota Utilities Co. North Dakota electric Rate 45, High Density Contracted Demand Response, is available for electric service to data center-type facilities housing high density computer processing technology with an expected demand of at least 10,000 kW per month at a single delivery point and an expected minimum load factor of 85 percent. Service must be interruptible for up to 200 hours a year or as the electric service agreement provides; each customer signs an electric service agreement of three to five years filed with and approved by the Public Service Commission and is billed the incremental costs of serving it.
- Geographic scope
- Montana-Dakota Utilities electric service area, North Dakota
- Jurisdiction
- Utility territory
- Authority type
- Utility
- Issuing authority
- Montana-Dakota Utilities Co.
Dates
- Adopted
- No adoption day is recorded
- Effective
- 1 July 2023
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The rate schedule states no expiration; service reverts to the otherwise applicable rate if the customer stops meeting the requirements.
- Source document
- 12 June 2023
- Last checked
- 3 November 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The Commission order approving Rate 45 in Case PU-22-337 (27 October 2022) is an image-only PDF and was not read; no adoption day is stored.
- The current sheets cite Case PU-22-194 (the 2022 electric rate case) and state service on and after 1 July 2023; whether earlier Rate 45 sheets took effect before that day was not determined.
- Individual electric service agreements under Rate 45, and Montana-Dakota Utilities rate cases pending in 2026, were not reviewed.
- The rate schedule applies within Montana-Dakota Utilities North Dakota service area only.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- No related action is recorded.
Sources
Primary source: Montana-Dakota Utilities Co. page on montana-dakota.com
- North Dakota Public Service Commission, Case PU-22-337 (High Density Contracted Demand Response) — Commission case in which Rate 45 was filed and an order entered on 27 October 2022 (order not read)