Summary
Minnesota's 2025 First Special Session chapter 12, signed on 14 June 2025, is an act relating to data centers. It added water-appropriation preapplication and permit provisions for large data-center water use, a statutory definition of a data center as a facility designed for a load of 100 megawatts or more, very-large-customer and clean-energy tariff sections for utilities, an annual fee on qualified large-scale data centers, and changes to the data-center sales-tax exemption for sales and purchases made after 30 June 2025. Most sections took effect the day after final enactment; the tax sections apply to sales and purchases made after 30 June 2025.
Scope
Minnesota Laws 2025, First Special Session, chapter 12 (H.F. 16) is an act relating to data centers. It states a state policy that data-center permitting inquiries are also referred to the Minnesota Business First Stop program; adds a preapplication evaluation for a data center whose proposed consumptive use exceeds 100,000,000 gallons per year (section 103G.265, subdivision 5) and water-use permit conditions for large data-center appropriations (section 103G.271, subdivision 5b); defines "data center" in section 216B.02, subdivision 11, as a facility designed to have a load of 100 megawatts or more whose primary purpose is the storage, management, and processing of digital data; adds section 216B.1622 (service to very large customers) and section 216B.1623 (a clean energy and capacity tariff for commercial and industrial customers); amends sections 216B.1691, 216B.2402 and 216B.241, including an exemption from energy conservation optimization contributions for a qualified large-scale data center that pays the section 216B.72 fee; adds the qualified large-scale data center fee in section 216B.72; and amends the sales-tax exemption in section 297A.68, subdivision 42, and the refund list in section 297A.75, subdivision 1, for sales and purchases made after 30 June 2025. The act does not impose a construction pause.
- Geographic scope
- Minnesota
- Jurisdiction
- State
- Authority type
- Legislature
- Issuing authority
- Minnesota Legislature
Dates
- Adopted
- 14 June 2025
- Effective
- Several dates apply; see the source
- Scheduled expiration
- No expiration date recorded
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- 14 June 2025
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- This is one record for the whole act. The water-permit conditions (section 103G.271, subdivision 5b) and the annual fee (section 216B.72) are also tracked as separate records because each is a codified section with its own operative text.
- Section 17 amended Minnesota Statutes section 297A.68, subdivision 42 (the data-center sales-tax exemption), which is tracked as a separate record; this record does not restate that exemption.
- Section 216B.1622 on very large customers, added by this act, does not itself name data centers, so it is not tracked as a separate data-center record.
- Sections 1, 2, 5 and 6 carry no effective-date clause in the opened text; this record does not compute their effective day, so the act has no single effective date.
- The record does not establish which facilities, if any, have paid the fee, sought a water-use permit under these provisions, or been certified for the tax exemption.
Unresolved questions
- Later amendments to each codified section are tracked on that section's own record, not here; the opened session-law page does not list later amendments to the act itself.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement Water-use permit conditions for large data centers (In effect)
- Related, not a replacement Annual fee on qualified large-scale data centers (In effect)
- Related, not a replacement Qualified data center sales-tax exemption (In effect)
Sources
Primary source: Minnesota Legislature page on revisor.mn.gov