Social Circle Technology Park

source-reported proposed

TPA Group (developer; end tenant undisclosed)

Social Circle · Newton County · Georgia

Capacity not statedSource updated 6 July 2026approximate location · provider confidence label: reported
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Social Circle Technology Park.

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
TPA Group (developer; end tenant undisclosed)
Address and locality
Social Circle · Newton County · Georgia
Official metro area
Atlanta-Sandy Springs-Roswell, GA
Source-reported status
proposed
Provider facility type
data center
Reported capacity
Not stated
Source freshness
6 July 2026
Location precision
approximate (provider label: exact; the provider's own note describes an approximate location)
Compute Atlas confidence label
reported (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-001483

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Georgia PowerUtility as named by the provider.
Power source
GridProvider label.
Cooling
Not establishedProvider label: unknown.
Land area
317 acres (source-reported; parcel boundary not established)
Announced investment
$5 billionAnnounced figure; whether it covers one building, a campus or a multi-phase program is not established.
Community response
Provider label: contestedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
likelyCompute Atlas classification, not a DataCenterData finding.
Announced
January 2025Provider-reported announcement date.

Provider notes

Energy. Georgia Power committed to serve the site via an on-site substation (June 2025); power demand not disclosed.

Water. Project representatives were in discussions with the Newton County Water & Sewerage Authority (June 2025), which states it has capacity; no volume or cooling type disclosed.

Community. Social Circle City Council unanimously approved a special-use permit for SC Infrastructure LLC (June 2025). A jurisdictional dispute exists — Newton County does not recognize the 2008 annexation of the site into Social Circle. Newton County enacted a 30-day moratorium on new data-center applications (April 2026); Social Circle and Covington enacted their own moratoriums. The project is "projected eventually to employ 200 people" (developer — a projection). No lawsuit against this specific project.

What the source record says

Nine buildings, 2.56 million sq ft near I-20/SR-11 intersection. Construction planned to begin 2028; first phase operational target 2031. Formerly filed as Newton County Technology Park; renamed after jurisdictional ambiguity surfaced. Coordinates corrected to Social Circle city centroid (33.6562°N, 83.7182°W); original record had 33.5912°N which is approximately 4.5 miles south of the actual city center per multiple geocoding sources.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025-01 · source-reported proposed

    TPA Group filed Development of Regional Impact application with Georgia Department of Community Affairs for nine-building campus near I-20 and SR-11

    Open cited source →

  2. 2025-04 · source-reported proposed

    Social Circle Planning Commission recommended approval 3-2 for rezoning from agricultural to light industrial; jurisdictional dispute with Newton County ongoing

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID tpa-social-circle-technology-park-ga. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-001483

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): likely

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Social Circle, GA · Newton (Approximate location)

Roles

  • Operator: TPA Group (developer; end tenant undisclosed)

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported proposed

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: January 2025

    Provider-reported announcement date.

  • Status history: 2025-01 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2025-04 · source-reported proposed

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 317 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Not stated

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Georgia Power

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Not established

    Provider label: unknown.

Permits, incentives, jobs and proceedings

  • Announced investment: $5 billion

    Announced figure; whether it covers one building, a campus or a multi-phase program is not established.

  • Community response: Provider label: contested

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-07-06

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →