Otter Tail Power Company South Dakota service area

Otter Tail proposed high power compute rate for data center load

Regulatory or tariff proceeding

Pending proceeding This is an open proceeding, not a final rule or tariff approval.

In plain English

Who it would affect: The proposed schedule would cover new high power computing customers, such as data centers or artificial intelligence, at a new location Otter Tail Power does not already serve. A customer would need to intend at least 75 MW of firm, meaning non-interruptible, service in South Dakota and keep an average annual load factor of at least 70%, except for scheduled outages.

What it would change: Each customer would pay the full cost of serving it, including generation dedicated to it. Contracts would run at least 15 years after a build-out period, and leaving early would take 36 months' notice plus an exit fee. A 29 September 2026 revision would also charge that fee to a customer that chooses not to renew.

Easy to misread: Nothing here has been approved: as of 3 November 2026 the docket page lists the case as pending and shows no orders.

  • Proposed minimum size: Firm electric service of at least 75 MW in South Dakota, metered at one point or added up across connected buildings on contiguous parcels run as a single campus (Section 10.07, Original Sheet No. 1)
  • Proposed load factor: Average annual load factor of at least 70%, except for scheduled outages (Section 10.07, Original Sheet No. 2)
  • Proposed limit on on-site generation: No behind the meter generation except for emergency backup, or usage during the build-out period as set out in the service agreement (Section 10.07, Original Sheet No. 2)
  • Proposed contract length: The build-out period plus no less than 15 years (Section 10.07, Original Sheet No. 2)
  • Proposed notice to leave early: Written notice 36 months before the requested termination date, plus an exit fee (Section 10.07, Original Sheet No. 12)
  • Proposed penalty for leaving before service starts: Reimbursement of all actual costs incurred or committed, subject to the company taking commercially reasonable steps to mitigate them, plus 10% of the value of the new transmission and distribution facilities planned for the customer (Section 10.07, Original Sheet No. 13)

Written from Otter Tail Power Company's petition in South Dakota PUC Docket EL26-021, read with its proposed Section 10.07 pages filed 5 August 2026 and its revisions filed 29 September 2026, read on 3 November 2026. A reading aid, not legal advice. The document controls.

Summary

Otter Tail Power Company petitioned the South Dakota Public Utilities Commission on 27 July 2026 to create a very large customer class and a new high power compute rate schedule for customers with at least 75 MW of firm data center load. The proposed take-or-pay service would assign data center costs to the data center, with a proposed start of 1 January 2027. The docket is pending and nothing has been approved. The current docket lists a 29 September 2026 supplemental filing and revised tariff revisions; it still labels the matter pending. The revisions keep the 75 MW line, the 70 percent load factor and the 15-year term, and change the credit support and early termination terms.

Scope

In South Dakota PUC Docket EL26-021, filed 27 July 2026, Otter Tail Power Company asks the Commission to approve a new class for very large customers, including a new Section 10.07 Large General Service Tier III High Power Compute rate schedule for customers with at least 75 MW of firm data center load, designed as a long-term take-or-pay service that assigns to the data center all costs attributable to serving data center load, with a proposed effective date of 1 January 2027.

Geographic scope
Otter Tail Power Company South Dakota service area
Jurisdiction
Utility territory
Authority type
Utility
Issuing authority
Otter Tail Power Company (petition filed with the South Dakota Public Utilities Commission)

Dates

Adopted
No adoption day is recorded
Effective
Not in effect (open proceeding)
Scheduled expiration
No expiration date recorded
Ended
Not recorded as ended
Completion condition
None stated
Source document
27 July 2026
Last checked
3 November 2026
About this date

This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.

What this does not establish

  • This is the utility's pending petition; as of 3 November 2026 the docket page shows the case as Pending with no orders listed.
  • The 5 August 2026 tariff pages and the 29 September 2026 letter and redline were read. The redline also strikes "full firm" from the Dedicated Resources definition and adds Non-Renewal and Stranded Costs terms.
  • The petition's references to parallel Minnesota and North Dakota filings are outside this state's records.

Unresolved questions

None recorded.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

Sources

Primary source: Otter Tail Power Company (petition filed with the South Dakota Public Utilities Commission) page on puc.sd.gov

Back to the policy tracker · South Dakota policy module