Executive Order JML 26-058: ratepayer and community protection conditions for data center incentives

Reporting or resource-use requirement

In effect This instrument is recorded as currently in effect as of the dataset date.

Scope

Executive Order JML 26-058 directs the Secretary of Louisiana Economic Development to develop and adopt a Ratepayer and Community Protection Framework for Large Load Investments that must be written into any agreement under R.S. 47:305.73(B) for the Data Center Sales and Use Tax Exemption and related incentives. Before a new data center is approved for, or continues to receive, those benefits, the project's demands on water, generation and transmission capacity, land and other resources must be evaluated against its benefits, and companies must file an attestation of their plan to meet the Framework. It does not change the statute and does not limit the Public Service Commission's jurisdiction.

Geographic scope
Louisiana
Jurisdiction
State
Authority type
Executive
Issuing authority
Governor of Louisiana

Dates

Adopted
25 June 2026
Effective
25 June 2026
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
The order remains in effect until amended, modified, rescinded by the Governor, or terminated by operation of law. The Secretary's proposed criteria and Framework are due to the Governor within 90 days of the order's effective date; that is a report deadline, not an expiration.
Source document
25 June 2026
Last checked
2 October 2026 (earlier than tracker date 5 October 2026; not an automatic status change)

Summary

On 25 June 2026 Governor Jeff Landry issued Executive Order JML 26-058, the Louisiana Ratepayer and Community Protection Initiative. It directs Louisiana Economic Development to develop a Ratepayer and Community Protection Framework that must be written as conditions into agreements for the Data Center Sales and Use Tax Exemption under R.S. 47:305.73(B) and related incentives for data centers and other large-load projects. The Framework's areas include large-load customers fully funding the generation, transmission and infrastructure needed to serve them, water and energy efficiency, local tax contributions, workforce and community investment, and transparency. Companies must file an attestation of their plan to comply. The order took effect on signature and states no end date.

What this does not establish

  • The text used is the Office of the State Register's published copy of the order (Division of Administration, .docx); the Governor's own PDF copy has only an OCR text layer and was not used for quotations.
  • The order directs an agency to develop criteria; the Framework itself, and whether the Governor has approved it, were not found or opened in this review.
  • The action type records the attestation and resource-evaluation conditions on an incentive; the order does not repeal or amend the exemption statute (record la-rs-47-305-73-data-center-sales-use-exemption).
  • The 90-day date for presenting the proposed Framework is a report deadline, not an expiration, and is not stored as a date.

Unresolved questions

  • Whether Louisiana Economic Development has adopted the Framework and applied it to any data center agreement was not established.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

Sources

Primary source

https://www.doa.la.gov/media/mpxjbua3/jml-26-058-data-center-framework-investments.docx

Back to the policy tracker · Louisiana policy module