Summary
AES Indiana asked the Indiana Utility Regulatory Commission on 22 April 2026 to approve generation and battery storage resources required primarily to serve a subsidiary of Alphabet, Inc. at a planned data center site in Monrovia, Indiana, together with construction, electric service and temporary service agreements with that customer. The case page listed the cause as pending when read on 23 September 2026; its current disposition was not verified. In AES Indiana's separate rate case, the Commission's 2 September 2026 order in Cause No. 46258 says it will rehear that case in the limited capacity of gathering new evidence concerning the Google Monrovia data center project and the BlackRock Acquisition. This is a customer-specific proceeding in the AES Indiana service territory, not a general tariff.
Scope
Indiana Utility Regulatory Commission Cause No. 46394 is reviewing a petition filed on 22 April 2026 by AES Indiana for approval of a project (generation, battery storage and related infrastructure) required primarily to serve a subsidiary of Alphabet, Inc. at a planned site in Monrovia, Indiana, and of the Construction Service, Electric Service and Temporary Service Agreements with that customer. The proposed order filed with the petition describes the site as a planned data center site, and the Commission's 2 September 2026 order in Cause No. 46258 refers to the Google Monrovia data center project as docketed under Cause No. 46394. The IURC case page showed the cause as pending on 23 September 2026.
- Geographic scope
- AES Indiana service territory, Indiana
- Jurisdiction
- State
- Authority type
- Regulator or commission
- Issuing authority
- Indiana Utility Regulatory Commission
Dates
- Adopted
- No adoption day is recorded
- Effective
- Not in effect (open proceeding)
- Scheduled expiration
- No expiration date recorded
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- 22 April 2026
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
- Proceeding
- IURC Cause No. 46394
What this does not establish
- This is an open proceeding on a utility petition, not a Commission approval; any order in Cause No. 46394 will be its own record.
- The data-center wording quoted comes from the proposed order filed with the petition and from the Commission's 2 September 2026 order in Cause No. 46258; the agreements themselves were not read.
- The IURC case page lists orders and filings through a script that could not be run automatically; only the served status fields (Petition Date, Case Status) were read.
- Project size, costs and contract prices are not restated.
- The petition and case page could not be re-opened on 3 November 2026, so the pending status still rests on the 23 September 2026 reading. The result of the rehearing set in Cause No. 46258 was not read.
Unresolved questions
- Whether and on what terms the Commission will approve the project and the customer agreements.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- No related action is recorded.
Sources
Primary source: Indiana Utility Regulatory Commission page on iurc.portal.in.gov
- IURC case page, Cause No. 46394 — proceeding status (Petition Date 04/22/2026; Case Status Pending)
- IURC order in Cause No. 46258 (approved 2 September 2026) — Commission text identifying the Google Monrovia data center project as docketed under Cause No. 46394 · 2 September 2026