Mesa, Arizona

Mesa: data centers only through council-authorized PAD overlay

Permanent restriction or prohibition · Mesa only (local rule)

In effect This instrument is recorded as currently in effect as of the dataset date.

Scope

Mesa Ordinance No. 5957 amends the Mesa zoning ordinance to define data center as a distinct land use and provides in the land use tables that a data center may be permitted only if specifically authorized by the City Council at the time of approval of a Planned Area Development overlay district, with standards for location, design, screening and noise adopted by reference. It is a City of Mesa zoning amendment and does not apply elsewhere in Arizona.

Geographic scope
Mesa, Arizona
Jurisdiction
Local
Authority type
Local government
Issuing authority
Mesa City Council

Dates

Adopted
8 July 2025
Effective
7 August 2025
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
The ordinance states no expiration. Its effective date is thirty days after adoption; 7 August 2025 is computed from the 8 July 2025 adoption.
Source document
8 July 2025
Last checked
23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)

Summary

Mesa Ordinance No. 5957, passed and adopted by the City Council on 8 July 2025, makes data center a distinct land use that may be permitted only when the City Council specifically authorizes it while approving a Planned Area Development overlay district, and adopts location, design, screening and noise standards by reference. The ordinance takes effect thirty days after adoption, computed as 7 August 2025. It does not order an existing facility to close.

What this does not establish

  • 7 August 2025 is computed from Section 10 (effective thirty days after adoption); the ordinance does not print the calendar day.
  • The Section 11-31-36 standards and PAD amendments adopted by reference (Resolution No. 12395) were not opened.
  • The ordinance provides a waiver path for certain owners and protects prior approvals; those provisions are not restated. Later amendments were not checked.

Unresolved questions

None recorded.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.

Sources

Primary source

https://mcclibraryfunctions.azurewebsites.us/api/ordinanceDownload/15749/1367318/pdf

    Back to the policy tracker · Arizona policy module