Brightseat Tech Park

source-reported permitted

Lerner Enterprises / The Tower Companies (Brightseat Associates LLC)

Landover · Prince George's County · Maryland

Reported planned 820 MWSource updated 13 September 2026exact location (provider label) · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Brightseat Tech Park.

Exact source coordinates (provider label); this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Lerner Enterprises / The Tower Companies (Brightseat Associates LLC)
Address and locality
Landover · Prince George's County · Maryland
Official metro area
Washington-Arlington-Alexandria, DC-VA-MD-WV
Source-reported status
permitted
Provider facility type
data center
Reported capacity
Planned: 820 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
13 September 2026
Location precision
exact (provider label)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-000861

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Pepco (Exelon)Utility as named by the provider.
Power source
GridProvider label.
Land area
87 acres (source-reported; parcel boundary not established)
Announced investment
$5 billionAnnounced figure; whether it covers one building, a campus or a multi-phase program is not established.
Community response
Provider label: opposedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
mixed useCompute Atlas classification, not a DataCenterData finding.
Announced
March 2024Provider-reported announcement date.

Provider notes

Energy. Prince George's County is Pepco (Exelon) service territory. The 820 MW campus holds final plan approvals but has been politically frozen since a September 2025 county-executive order and a council moratorium, so interconnection/PJM and on-site generation details remain undisclosed.

Community. 22,500+ petition signatures collected. County Executive Aisha Braveboy issued executive order in September 2025 pausing development. Separately, the Prince George's County COUNCIL passed a county-wide TWO-YEAR moratorium on hyperscale data center development -- a distinct action from the County Executive's September 2025 executive-order pause above, and reported by WTOP on 2026-07-07 (the article states no vote date, so 2026-07-07 is the REPORTING date, not the vote date). …

What the source record says

2101 Brightseat Road, Landover MD. Project has final plan approvals but is politically frozen pending task force report. Five buildings on 87 acres of former mall site. As a permitted-but-frozen project, no facility-specific water design, subsidy award, or committed job figures have been disclosed; job figures circulating in press are Maryland Tech Council sector benchmarks, not Brightseat commitments. Re-checked 2026-09-10: status remains PERMITTED (no enum value exists for 'construction paused by opposition/moratorium'). Groundbreaking has not occurred; community opposition (23,000+ petition signatures) and PG County Council ordinances CB-019-2026/CB-020-2026 (introduced March 2026 to repeal the qualified-data-center site-plan-review exemption) continue to threaten the timeline. Subsidies: found only a general-program reference (MD/PG County 2020 sales-and-use tax exemption for qualified data centers, Tax-General Article Sec.11-239(a)(5)(i)) with no site-specific dollar figure for this project, so no subsidies entry is reported -- record as a program-level fact only. No street-address source was independently fetched this run (existing statusHistory note already cites 2101 Brightseat Road from an earlier source), so location.street is left for a future run with a fresh citation.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2024-03 · source-reported proposed

    Prince George's County Planning Board approved 4.1 million sq ft, five-building campus at 2101 Brightseat Road (former Landover Mall site, demolished 2006)

    Open cited source →

  2. 2024-10 · source-reported permitted

    Final plan approvals received October 2024 under 2021 county law bypassing Council review. Groundbreaking target 2026 or 2027.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID lerner-brightseat-tech-park-md. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-000861

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): mixed use

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Landover, MD · Prince George's (Exact location)

Roles

  • Operator: Lerner Enterprises / The Tower Companies (Brightseat Associates LLC)

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported permitted

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: March 2024

    Provider-reported announcement date.

  • Status history: 2024-03 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2024-10 · source-reported permitted

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 87 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 820 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Pepco (Exelon)

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Permits, incentives, jobs and proceedings

  • Announced investment: $5 billion

    Announced figure; whether it covers one building, a campus or a multi-phase program is not established.

  • Community response: Provider label: opposed

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-09-13

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →