Power · PA

Air Permit clears the way for full construction of 4.4-GW natural gas-powered energy and data center campus, with initial power production targeted for 2027.

A verdict applies only to the wording shown.

Public statement checked

Answer

Verdict on the wording above: Partially supported as of Developer release and DEP page read 1 November 2026 Independent evidence supports part of the claim; the rest is unknown or unsupported. The full statement is not thereby false. How verdicts work →

Who stated it
Said by Homer City Generation · company statement in PRESS RELEASE: Homer City Generation Receives Air Quality Plan Approval from PA DEP · 20 November 2025 →
What the evidence establishes
Partly. Pennsylvania's Department of Environmental Protection lists a Final Air Quality Plan Approval, 32-00457A, dated 18 November 2025, for the Homer City generation redevelopment. The developer's release describes it as authorizing the gas generating facility. The DEP page does not show the 4.4 GW figure or data center scope, the 2027 target is unverified, and an approval is permission, not construction.
Biggest limitation
The text of Plan Approval 32-00457A (number and rating of turbines, permitted capacity), DEP's comment response on data center scope, whether construction has begun, whether power production will start in 2027, and any data center tenant. The plan approval documents could not be read.
Checked
1 November 2026 · Next review: The text of Plan Approval 32-00457A and DEP's comment response, or a DEP record of construction or operation

Evidence

What the evidence supports

DEP's Homer City Generation Site Redevelopment page lists 'Final Plan Approval 32-00457A (November 18, 2025)' with its technical review memo and comment response, and describes the site as a decommissioned 2 GW coal plant to be transformed into a more than 3,200-acre natural gas-powered data center campus. The developer's release says the approval 'authorizes construction and initial operation of the natural gas generating facility' and that, once fully developed, the facility is expected to deliver up to 4.4 gigawatts. So an air approval for the gas generating plant is supported. The release's own body describes the authorization as covering the natural gas generating facility. The 4.4 GW figure and any authorization of data center buildings are not shown in the DEP page read, and the 2027 target for initial power production is not verified.

Still unknown

The text of Plan Approval 32-00457A (number and rating of turbines, permitted capacity), DEP's comment response on data center scope, whether construction has begun, whether power production will start in 2027, and any data center tenant. The plan approval documents could not be read.

Sources

  1. PRESS RELEASE: Homer City Generation Receives Air Quality Plan Approval from PA DEP → Company

    Exact location Subheadline; first and third paragraphs.

    What it supports The statement checked and the release's description of what the approval authorizes.

    Publication date · Accessed

  2. Homer City Generation Site Redevelopment → Gov. record

    Exact location Background section; 'Final Air Quality Plan Approval Documents' list.

    What it supports A final plan approval, 32-00457A, was issued on 18 November 2025 for the generation redevelopment.

    Publication date unavailable · Accessed

Review details

Scope

Unit
air quality plan approval scope and planned generation capacity
Geography
Homer City Generation, former Homer City Generating Station site, Indiana County, Pennsylvania
Period
plan approval 18 November 2025; release 20 November 2025
As of
Developer release and DEP page read 1 November 2026
Confidence
medium — DEP project page listing the final plan approval and its date; the approval itself was not read.
Kind
Public statement checked

Conflicting evidence

None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.

Chronology

  1. Stated by Homer City Generation
  2. Published — PRESS RELEASE: Homer City Generation Receives Air Quality Plan Approval from PA DEP
  3. 2 sources retrieved
  4. Checked by DataCenterData
  5. Date not established Next review: The text of Plan Approval 32-00457A and DEP's comment response, or a DEP record of construction or operation

Corrections and history

No corrections or wording changes recorded for this claim.

Data

This claim as JSON →

Suggest a correction

Suggest a correction → Claim ID pa-homer-city-air-permit-data-center-campus and this page are prefilled. Accepted material corrections appear publicly on Changes.