Hillsdale Township Ordinance No. 2026-06-01 adopts a temporary moratorium on the acceptance and/or processing of any applications for a Data Center in Hillsdale Township, Hillsdale County, while the township studies its ordinances and regulations and considers revisions. The official copy contains no definition of data center and no exemptions. Section III allows the Township Board to extend the moratorium by resolution before it expires.

Geographic scope
Hillsdale Township, Michigan
Jurisdiction
Local
Authority type
Local government
Issuing authority
Hillsdale Township Board of Trustees

Dates

Adopted
9 June 2026
Effective
24 June 2026
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
Section II keeps the moratorium in effect for one year from the effective date of the ordinance (printed as 24 June 2026), or until amended or new township ordinances or regulations addressing data centers are effective, whichever occurs first; Section III allows the Township Board to extend it by resolution before it expires. No calendar end date is printed, so none is stored.
Source document
The source page states no document date
Last checked
1 November 2026

Summary

The Hillsdale Township Board of Trustees in Hillsdale County adopted Ordinance No. 2026-06-01 on 9 June 2026, and the township's official copy prints an effective date of 24 June 2026. The ordinance places a temporary moratorium on the acceptance and processing of any applications for a data center while the township studies its ordinances and considers revisions. It runs for one year from the effective date or until new or amended township rules on data centers take effect, whichever comes first, and the board may extend it by resolution. It is a temporary moratorium, not a permanent prohibition.

What this does not establish

  • The source is the township's posted copy of the ordinance, which prints its ADOPTED and EFFECTIVE dates; no adoption minutes, vote record or publication notice were reviewed.
  • The ordinance does not define data center.
  • No calendar end date is printed; the one-year term runs from the printed effective date.
  • The ordinance applies only in Hillsdale Township, Hillsdale County.

Unresolved questions

  • Whether the Township Board extends the moratorium or adopts data center regulations before the one-year term ends.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.