Scope
H.727, as passed by the House and the Senate, would have added the Vermont Sustainable Data Centers Act to 30 V.S.A. chapter 5, defining a data center as a facility that uses or is able to use 20 megawatts or more of power and is engaged in data processing, hosting and related services under NAICS code 518210, and requiring the Public Utility Commission to establish a separate ratepayer class and tariff schedule applicable to data centers and specific provisions in data center electric service contracts. The Governor returned it unsigned on 28 May 2026, and the veto was sustained on 29 May 2026 by Yeas 83, Nays 52. It did not become law.
- Geographic scope
- Vermont
- Jurisdiction
- State
- Authority type
- Legislature
- Issuing authority
- Vermont General Assembly
Dates
- Adopted
- No adoption day is recorded
- Effective
- Never took effect (vetoed)
- Scheduled expiration
- None scheduled
- Ended
- 29 May 2026
- Completion condition
- None stated
- Source document
- The source page states no document date
- Last checked
- 23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)
Summary
H.727, as passed by both houses, would have created the Vermont Sustainable Data Centers Act with a 20-megawatt data center definition and a Public Utility Commission rate class, tariff and contract framework for data centers. The Senate Journal records the Governor's veto of 28 May 2026, and the bill status page records that the veto was sustained on 29 May 2026. The bill did not become law.
What this does not establish
- The bill PDF is the text as passed by both houses; it does not itself record the veto. The veto day is from the 28 May 2026 Senate Journal and the sustain vote from the bill status page.
- The end date recorded here is the day the veto was sustained (29 May 2026); the veto communication is dated 28 May 2026.
- The tariff and contract duties in the bill were not established as Public Utility Commission orders.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement Veto of H.727 sustainable data center deployment bill (Completed)
- Related, not a replacement Commercial energy-code requirements for data center rooms (In effect)
Sources
https://legislature.vermont.gov/Documents/2026/Docs/BILLS/H-0727/H-0727%20As%20Passed%20by%20Both%20House%20and%20Senate%20Official.pdf
- H.727 bill status (Vermont General Assembly) records the veto sustained on 29 May 2026
- Senate Journal, 28 May 2026 prints the Governor veto communication · 28 May 2026