City of Reno, Nevada

Reno: pause on data center conditional use permit applications to 31 August 2027 (council resolution)

Local construction moratorium · Reno only (local rule)

Adopted; effective status unverified This instrument was adopted; whether it has taken effect has not been verified.

Scope

A City of Reno moratorium resolution related to data center development, approved by the City Council on 1 June 2026. The city states that it will not accept applications for conditional use permit requests for data centers during the moratorium, and that all new data centers attempting to develop in the City of Reno require approval of a conditional use permit. The city states that the moratorium runs through 31 August 2027 or until adequate regulations are adopted.

Geographic scope
City of Reno, Nevada
Jurisdiction
Local
Authority type
Local government
Issuing authority
Reno City Council

Dates

Adopted
1 June 2026
Effective
Effective status not verified
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
The city states: 'The moratorium is in effect through August 31, 2027, or until a time that adequate regulations are adopted.' The record's status (effect not verified from the resolution) does not carry a stored end; the stated end is 31 August 2027.
Source document
The source page states no document date
Last checked
30 October 2026

Summary

The City of Reno reports that on 1 June 2026 the City Council approved a final moratorium resolution on data center development. According to the city, Reno will not accept conditional use permit applications for data centers, which every new data center in the city needs, through 31 August 2027 or until adequate regulations are adopted. The city's page does not print the day the resolution took effect. It is a temporary pause on applications, not a permanent prohibition.

What this does not establish

  • The evidence is the city's Development Services initiatives page. The resolution text, its number and the vote were not opened.
  • The page prints no effective day for the resolution; the 31 August 2027 end it states is given in the completion condition.
  • The page calls this a final moratorium resolution; any earlier interim action is not described there and is not recorded here.
  • A separate text amendment to Title 18 on data center regulations, initiated on 22 April 2026, is a pending measure and is not recorded here.

Unresolved questions

  • The day the resolution took effect is not stated on the city's page.
  • Whether the council adopts data center regulations that end the moratorium before 31 August 2027.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.