Summary
New Hampshire House Bill 1265 of 2026 proposed a one-year statewide moratorium on beginning construction of new data centers and a legislative study committee on their environmental impact. The committee recommended inexpedient to legislate by a 15-0 vote, and the House adopted that report by voice vote on 11 March 2026, so the bill did not pass.
Scope
New Hampshire House Bill 1265 (2026), as introduced, would have provided that no person, business or entity shall begin construction of a new data center in New Hampshire from the act's effective date through one year following, defining a data center as a facility of a large group of networked computer servers used for the remote storage, processing or distribution of large amounts of data, and would have established a legislative committee to study the environmental impact of data centers. The House voted it inexpedient to legislate on 11 March 2026.
- Geographic scope
- New Hampshire
- Jurisdiction
- State
- Authority type
- Legislature
- Issuing authority
- New Hampshire General Court
Dates
- Adopted
- No adoption day is recorded
- Effective
- Never took effect (did not pass)
- Scheduled expiration
- No expiration date recorded
- Ended
- 11 March 2026
- Completion condition
- None stated
- Source document
- The source page states no document date
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The record uses the bill as introduced; no amended version was opened.
- The bill never took effect; it does not describe any restriction that applies in New Hampshire.
- The official docket records how the bill ended; it does not establish that any later 2026 or 2027 bill with similar content was or was not filed.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- No related action is recorded.
Sources
Primary source: New Hampshire General Court page on gc.nh.gov
- New Hampshire General Court official bill docket — records the votes and the day the bill ended