Big Rapids Charter Township, Michigan

Big Rapids Charter Township: one-year data center moratorium (Data Center Moratorium Ordinance)

Local construction moratorium · Big Rapids Charter Township only (local rule)

Adopted; effective status unverified This instrument was adopted; whether it has taken effect has not been verified.

Scope

The Big Rapids Charter Township Data Center Moratorium Ordinance enacts a temporary moratorium on the permitting, consideration, approval, location, erection, construction, review, and/or installation of all Data Centers in the Township for one year, subject to extensions of six months or less by resolution, or the Township's implementation of regulations governing Data Centers. Data Center means a facility used primarily for the storage, management, processing and transmission of digital data, and the moratorium encompasses all like operations. Section 6 lets a landowner apply for a waiver if the Township Board extends the moratorium beyond 12 months.

Geographic scope
Big Rapids Charter Township, Michigan
Jurisdiction
Local
Authority type
Local government
Issuing authority
Big Rapids Charter Township Board

Dates

Adopted
23 February 2026
Effective
Effective status not verified
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
Section 3 sets a term of one year, subject to extensions of six months or less by resolution, or until the Township implements regulations governing Data Centers. The ordinance does not print the day the year begins; Section 7 ties effect to passage and publication, and no publication date is shown.
Source document
23 February 2026
Last checked
30 October 2026

Summary

The Big Rapids Charter Township Board adopted a Data Center Temporary Moratorium Ordinance on 23 February 2026 by a 6-0 vote. It places a one-year temporary moratorium on the permitting, consideration, approval, location, construction, review and installation of all data centers in the township, subject to extensions of six months or less by resolution, or until the township adopts data center regulations. The ordinance says it takes effect upon passage and publication, and the publication date is not shown. It is a temporary moratorium, not a permanent prohibition.

What this does not establish

  • The posted copy carries no ordinance number.
  • The posted copy does not show the publication date, so the effective date and the day the one-year term ends are not confirmed.
  • The clerk's certification describes the document as a resolution adopted at a special board meeting on 23 February 2026; Section 4 states the provisions are both an ordinance upon publication and a resolution of the Township Board.

Unresolved questions

  • When the ordinance was published and therefore took effect, and the day its one-year term ends.
  • Whether the Township Board extended the moratorium or adopted data center regulations.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.