Scope
The California Public Utilities Commission is considering Pacific Gas and Electric Company Advice Letter 7785-E, filed 18 December 2025, an exceptional case submittal under Electric Rules 2, 15 and 16 for an agreement to energize a new 250 megawatt data center load through transmission-level retail service for Google LLC in San Jose. Draft Resolution E-5455 proposes approval with modifications, including an additional capital advance of $600,000 per MW and limits on refunds. The draft was listed on the 17 September 2026 consent agenda; a revised draft dated 8 October 2026 was published on 22 September 2026. No adopted resolution is recorded.
- Geographic scope
- Pacific Gas and Electric service territory, California
- Jurisdiction
- State
- Authority type
- Regulator or commission
- Issuing authority
- California Public Utilities Commission
Dates
- Adopted
- No adoption day is recorded
- Effective
- Not in effect (open proceeding)
- Scheduled expiration
- None scheduled
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- 22 September 2026
- Last checked
- 2 October 2026 (earlier than tracker date 5 October 2026; not an automatic status change)
Summary
PG&E asked the California Public Utilities Commission in December 2025 (Advice Letter 7785-E) to approve an agreement to energize a new 250 megawatt data center load for Google LLC at transmission level. Draft Resolution E-5455 would approve it with modifications, including an added capital advance and limits on refunds. The item was listed on the 17 September 2026 consent agenda; a revised draft dated 8 October 2026 was published on 22 September 2026, and no final resolution is listed.
What this does not establish
- This is a draft resolution on a pending advice letter, not an adopted Commission decision; if adopted, the final resolution will be its own record.
- The October 8, 2026 date is the date printed on the revised draft, not an adoption or effective date.
- Cost figures in the draft may change before adoption.
Unresolved questions
- Whether the Commission adopts, modifies or rejects the draft resolution.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement CPUC Resolution E-5420: PG&E transmission energization agreement for a STACK Infrastructure data center (In effect)
- Related, not a replacement CPUC Resolution E-5439: PG&E transmission energization agreement for a Microsoft data center (In effect)
- Related, not a replacement CPUC Resolution E-5433: PG&E transmission energization agreement for a Menlo Equities data center (In effect)
Sources
https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M620/K406/620406422.PDF
- CPUC document search listing for E-5455 official listing of draft versions (latest published 09/22/2026)
- CPUC voting meeting agenda, 17 September 2026 consent agenda listing of Res E-5455