In plain English
Who it covers: As the city's hearings page describes it, the pause covers new data center applications and City development approvals in Memphis.
What it provides: The city's pages say the Council passed a pause of up to 135 days, ending sooner if permanent land-use and siting rules take effect. City planners are to provide a zoning and siting analysis within 45 days and proposed regulations within 90 days.
Easy to misread: This is not the permanent rule, and the adopted text could not be read: the city says planners are drafting recommendations for regulating future data centers.
- Length, as the city describes it: Up to 135 days, ending sooner if permanent land-use and siting regulations become effective (City hearings page)
- Zoning and siting analysis: Within 45 days (City hearings page)
- Proposed regulations: Within 90 days (City hearings page)
Written from City of Memphis page on the data center legislation hearings, read on 3 November 2026. A reading aid, not legal advice. The document controls.
Summary
The City of Memphis says its City Council passed a 135-day moratorium on new data center approvals. A city recap of the 26 October 2026 committee session refers to the recently passed 135-day pause within Substitute Ordinance No. 5986. The city's hearings page says the substitute would pause new data center applications and City development approvals for up to 135 days, ending sooner if permanent land-use and siting regulations become effective. The adopted text, vote, passage date and effective date could not be read.
Scope
City of Memphis Substitute Ordinance No. 5986, as the city's hearings page summarizes it, would temporarily pause new data center applications and City development approvals for up to 135 days, ending sooner if permanent land-use and siting regulations become effective, and directs the Division of Planning and Development to provide a zoning and siting analysis within 45 days and proposed regulations within 90 days. The city says the Council passed the pause. An earlier unsigned text in the 15 September 2026 agenda documents set broader standards for data centers; whether any of it was adopted was not established.
- Geographic scope
- City of Memphis, Tennessee
- Jurisdiction
- Local
- Authority type
- Local government
- Issuing authority
- Memphis City Council
Dates
- Adopted
- No adoption day is recorded
- Effective
- Effective status not verified
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The city describes a pause of up to 135 days, ending sooner if permanent land-use and siting regulations become effective. No start date was read, so no end date is computed.
- Source document
- The source page states no document date
- Last checked
- 3 November 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The adopted text, vote count, passage date and effective date could not be read. What is recorded here comes from city statements about the action, not from the ordinance.
- The same hearings page uses both the conditional, "would temporarily pause", and the past tense, "the Council's passing of a 135-day moratorium".
- The council agendas page, read on 3 November 2026, links no minutes for any meeting after 7 July 2026.
- An earlier unsigned text in the 15 September 2026 agenda documents applied to every new data center proposed after its effective date, with a 20 megawatt line for large facilities. It carries no ordinance number and is matched to this number by its title on the 20 October 2026 agenda. Whether any of it was adopted was not established.
- That earlier text recites that the Council "enacted Ordinance No. 5982". That recital does not show adoption: the 20 October 2026 agenda still lists Ordinance No. 5982 for third and final reading.
Unresolved questions
- The adoption date is unknown.
- In what text Substitute Ordinance No. 5986 was adopted and when the pause took effect.
- Whether any of the earlier standards text was kept.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement Memphis: proposed temporary data center permit moratorium (Ord. 5982) (Proposed)
Sources
Primary source: Memphis City Council page on memphistn.gov
- City recap of the 26 October 2026 committee session — refers to the recently passed 135-day pause within Substitute Ordinance No. 5986; read on 3 November 2026 · 26 October 2026
- 20 October 2026 council agenda — Latest proceeding agenda found; reading stage only, not a vote or adopted ordinance · 20 October 2026
- Recessed 6 October 2026 council agenda — Notes the request to hold the item until 20 October 2026 · 6 October 2026
- City Council agendas and minutes page — Links no council minutes after 7 July 2026 when read on 3 November 2026
- 15 September 2026 council agenda documents — earlier unsigned text; not shown as adopted · 15 September 2026