ZeroC / Petawatt Holdings Data Center Site (417 County Route 42)

source-reported proposed

ZeroC Data Centers LLC (majority-owned by Petawatt Holdings, Inc.)

417 County Route 42 · Massena · St. Lawrence County · New York · 13662

Reported planned 200 MWSource updated 21 September 2026approximate location · provider confidence label: reported
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for ZeroC / Petawatt Holdings Data Center Site (417 County Route 42).

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
ZeroC Data Centers LLC (majority-owned by Petawatt Holdings, Inc.)
Address and locality
417 County Route 42 · Massena · St. Lawrence County · New York · 13662
Official metro area
Outside an official metropolitan boundary
Source-reported status
proposed
Provider facility type
data center
Reported capacity
Planned: 200 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
21 September 2026
Location precision
approximate
Compute Atlas confidence label
reported (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-001636

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Massena Electric Department (MED)Utility as named by the provider.
Land area
14 acres (source-reported; parcel boundary not established)
Announced
January 2025Provider-reported announcement date.

Provider notes

Energy. Applicant told the planning board the substation would sit in MED service territory, interconnecting via the Dennison 115 kV substation (NYISO queue #1213/#1731).

What the source record says

Site preparation (brush clearing) and a ~$30M substation were approved in Feb 2025 to hold a NYISO queue position; the deed is in ZeroC Data Centers' name with Petawatt as majority shareholder. Applicant estimated a ~900,000 sq ft building and an employment ratio of 40–60 people per 100 MW, and offered to guarantee no cryptocurrency mining. Two containers of crypto mining were on the parcel at the time. NYISO queue shows a 200 MW request (#1213, 2021) and a later 300 MW request (#1731, March 2025) at the Dennison 115 kV substation. No building application found this session. Coordinates are a road-level geocode of County Route 42 near Dennison Road, not a confirmed parcel point.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025-02-20 · source-reported proposed

    Massena Town Planning Board approved (4-0) the site plan for a ~$30M substation at 417 County Route 42 intended to serve a future data center; applicant said the site is 'currently a 200 Megawatt site' and would start construction within 60 days of approval

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1+reviewed-2610e0556b3d, under CC BY 4.0. Upstream ID petawatt-zeroc-massena-ny. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labelled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-001636

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

Location and precision

  • 417 County Route 42, Massena, NY 13662 · St. Lawrence (Approximate location)

Roles

  • Operator: ZeroC Data Centers LLC (majority-owned by Petawatt Holdings, Inc.)

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported proposed

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: January 2025

    Provider-reported announcement date.

  • Status history: 2025-02-20 · source-reported proposed

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 14 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 200 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Massena Electric Department (MED)

    Utility as named by the provider.

Sources, dates, limitations and corrections

  • Provider update date: 2026-09-21

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact · Permits, incentives, jobs and proceedings.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.