  "schema_version": "0.3",
  "target_standard": "/data/state-data-standard.json",
  "last_reviewed": "2026-09-12",
  "coverage": {
    "verified_project_or_campus_records": 9,
    "related_child_records": 3,
    "unresolved_record_groups": 0,
    "unit": "named project or campus; child expansion projects and unresolved groups are listed and not added",
    "complete_statewide_census": false,
    "claim": "9 independently counted Indiana project/campus records after requiring qualifying primary evidence, plus one nonphysical NIPSCO contract ledger. The CoreWeave Hammond expansion and two Hobart permit sites are child records, not extra campuses. The NIPSCO ledger is excluded from project/campus and physical-capacity denominators. Company-only rows remain visible as attributed records.",
    "exclusions": "Colocation facilities remain in the facility inventory. Discovery candidates stay in candidate_queue."
  },
  "method_note": "Each project enters this ledger only after a primary government, regulatory, contractual or first-party project record confirms it. First-party values remain labeled as claims. Unknown never means zero.",
  "id_reconciliation": {
    "retired_duplicate_registers": [
      "indiana-census.json:large_projects",
      "indiana-projects.json:projects as a second 8-row authority"
    ],
    "canonical_aliases": {
      "microsoft-la-porte-1": "microsoft-la-porte",
      "digital-crossroads-hammond": "digital-crossroads-hammond",
      "coreweave-hammond": "coreweave-hammond"
    },
    "unit_note": "Digital Crossroads Hammond is the campus; CoreWeave Hammond is the expired expansion project; DX-1 is the operating facility."
  },
  "projects": [
    {
      "id": "google-fort-wayne",
      "stable_id": "google-fort-wayne",
      "aliases": [],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Google — Fort Wayne",
      "former_names": [],
      "state": "IN",
      "city": "Fort Wayne",
      "county": "Allen",
      "owner": "Google",
      "developer": "Google",
      "operator": "Google",
      "utility": "Indiana Michigan Power",
      "iso": "PJM",
      "acres": null,
      "lifecycle_status": "operating",
      "status_basis": "I&M stated that it energized the site in November 2024 and Google began operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Indiana Utility Regulatory Commission final order, Cause No. 46276",
          "url": "https://www.in.gov/iurc/files/ord_46276_042926.pdf",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://www.in.gov/iurc/files/ord_46276_042926.pdf",
          "source_type": "government"
        },
        {
          "title": "IEDC project announcement",
          "url": "https://www.iedc.in.gov/events/news/details/2024/04/26/gov.-holcomb-announces-google-is-building-a-2b-data-center-in-northeast-indiana",
          "type": "government announcement",
          "published": "2024-04-26",
          "retrieved": "2026-09-11",
          "locator": "https://www.iedc.in.gov/events/news/details/2024/04/26/gov.-holcomb-announces-google-is-building-a-2b-data-center-in-northeast-indiana",
          "source_type": "government"
        },
        {
          "title": "Data Center Tax Exemption Agreement, Hatchworks LLC (IEDC Project ID 424313)",
          "url": "https://transparencyportal.iedc.in.gov/iedc-transparency-api/api/contract/819d3f16ab5cee11be6e001dd804e4b1/pdf",
          "type": "executed state incentive agreement",
          "published": "2024-01-01 commencement",
          "retrieved": "2026-09-11",
          "locator": "Exhibit A, sections 1.A-1.B and 2.A-2.B (page 13 of 18); Exhibit C List of Affiliates",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Fort Wayne",
        "county": "Allen",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [
        {
          "date": "2026-09-11",
          "field": "record",
          "summary": "previously '35-year state sales-tax exemption for at least $800M eligible capital, with extensions tied to additional eligible investment up to 50 years.' The $800M figure is the announcement's wording; the executed agreement (Exhibit A, section 2.A, page 13 of 18) says $845,000,000. The IEDC portal's separate 'expected qualified investment' field ($830M) is a different field and is not used here."
        }
      ],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "I&M confirms the site was energized in November 2024 and Google began operation; construction continues. Project demand and acreage remain unknown pending independent support.",
      "profile_url": null,
      "verified_fields": [
        "utility filing",
        "energization milestone"
      ],
      "announced_investment": {
        "value": "$2 billion",
        "kind": "government-reported company plan",
        "scope": "Fort Wayne data center"
      },
      "permanent_jobs": {
        "value": "up to 200",
        "kind": "announced",
        "observed": "not yet reconciled"
      },
      "power_detail": {
        "value": "contract-specific value not established in this ledger",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "Cooling architecture, source-water mix and measured consumption are not established in the reviewed records.",
        "kind": "unknown"
      },
      "incentives_commitments": "IEDC's 2024 announcement described a 35-year state sales-tax exemption for a minimum $800M in eligible capital. The executed IEDC data-center tax exemption agreement with Hatchworks LLC (Project ID 424313; Google LLC is listed as an affiliate) sets the Minimum Qualified Investment at $845M by 31 December 2028 for an exemption deadline of 31 December 2059, extendable to 2064, 2069 or 2074 with at least $1.6B, $2.4B or $3.2B of qualified investment by 31 December 2038.",
      "next_check": "Obtain water permits or utility records and compare observed employment and eligible investment with the announced values.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "meta-lebanon",
      "stable_id": "meta-lebanon",
      "aliases": [],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Meta — Lebanon",
      "former_names": [],
      "state": "IN",
      "city": "Lebanon",
      "county": "Boone",
      "owner": "Meta",
      "developer": "Meta",
      "operator": "Meta",
      "utility": "Wabash Valley Power Alliance / Boone REMC",
      "iso": "MISO",
      "acres": 1500,
      "lifecycle_status": "construction",
      "status_basis": "Meta and IEDC reported a February 2026 groundbreaking; the underlying community-payment agreement has not been reviewed.",
      "capacity": {
        "value": 1000,
        "unit": "MW",
        "kind": "company_design",
        "scope": "campus",
        "aggregation_allowed": false,
        "note": "Company design claim; electric-demand, critical-IT-load and utility-contract boundaries are not established in the reviewed source."
      },
      "sources": [
        {
          "title": "Meta newsroom announcement",
          "url": "https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/",
          "source_type": "company"
        },
        {
          "title": "IEDC groundbreaking release",
          "url": "https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district",
          "type": "government announcement",
          "published": "2026-02-11",
          "retrieved": "2026-09-11",
          "locator": "https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [],
      "location": {
        "city": "Lebanon",
        "county": "Boone",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "Meta and IEDC reported a February 2026 groundbreaking; 1 GW is a company design claim, not measured load. IEDC describes 13 buildings, including 10 data-center buildings, across 1,500 acres.",
      "profile_url": "/projects/meta-lebanon/",
      "verified_fields": [
        "owner",
        "groundbreaking",
        "design claim"
      ],
      "announced_investment": {
        "value": "more than $10 billion",
        "kind": "company plan",
        "scope": "up to six phases"
      },
      "construction_jobs": {
        "value": "more than 4,000 at peak",
        "kind": "government-reported company projection"
      },
      "permanent_jobs": {
        "value": "approximately 300",
        "kind": "company projection",
        "observed": "not reconciled; enforceable deadline not established"
      },
      "power_detail": {
        "value": "1 GW designed capacity once operational",
        "kind": "company design claim"
      },
      "cooling_water": {
        "value": "Meta says closed-loop liquid cooling will recirculate water and use zero cooling water for most of the year; no operating result exists yet.",
        "kind": "company design claim"
      },
      "incentives_commitments": "35-year state sales-tax exemption for at least $1B eligible capital with extensions; $1.5M annual city impact payment for each completed phase; Meta says it will invest more than $120M in water and other infrastructure.",
      "next_check": "Obtain the underlying impact-payment and utility agreements; track each of up to six phases separately and test Meta's ratepayer and water claims after operation.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "meta-jeffersonville",
      "stable_id": "meta-jeffersonville",
      "aliases": [],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Meta — Jeffersonville",
      "former_names": [],
      "state": "IN",
      "city": "Jeffersonville",
      "county": "Clark",
      "owner": "Meta",
      "developer": "Meta",
      "operator": "Meta",
      "utility": "Duke Energy Indiana",
      "iso": "MISO",
      "acres": 619,
      "lifecycle_status": "construction",
      "status_basis": "IEDC reported the campus nearing completion in February 2026. That update does not establish operation, so the record remains construction.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Indiana Economic Development Corporation announcement",
          "url": "https://iedc.in.gov/events/news/details/2024/01/25/gov.-holcomb-announces-meta-to-build-an-800m-data-center-campus-in-indiana",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://iedc.in.gov/events/news/details/2024/01/25/gov.-holcomb-announces-meta-to-build-an-800m-data-center-campus-in-indiana",
          "source_type": "government"
        },
        {
          "title": "IEDC Lebanon groundbreaking release",
          "url": "https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district",
          "type": "government status update",
          "published": "2026-02-11",
          "retrieved": "2026-09-11",
          "locator": "https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure",
        "independently located construction-completion or operating milestone"
      ],
      "location": {
        "city": "Jeffersonville",
        "county": "Clark",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "IEDC reported the approximately 700,000-square-foot campus nearing completion in February 2026. Operation is not marked delivered. The 2024 announcement describes a 619-acre site and a 2026 expected-operation target; neither establishes current operation.",
      "profile_url": null,
      "verified_fields": [
        "owner",
        "location",
        "announced construction"
      ],
      "announced_investment": {
        "value": "$800 million",
        "kind": "government-reported company plan",
        "scope": "approximately 700,000-square-foot campus"
      },
      "permanent_jobs": {
        "value": "approximately 100",
        "kind": "announced operational jobs",
        "observed": "not reconciled; enforceable delivery deadline not established"
      },
      "construction_jobs": {
        "value": "more than 1,250 at peak",
        "kind": "government-reported company projection"
      },
      "power_detail": {
        "value": "not established in the reviewed primary records",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "Architecture and measured water use are not established in the reviewed primary records.",
        "kind": "unknown"
      },
      "incentives_commitments": "35-year state sales-tax exemption tied to at least $800M of eligible capital, with a five-year extension for each additional $800M up to 50 years; benefits accrue only after qualifying investment. River Ridge and other local terms remain unquantified pending underlying agreements.",
      "next_check": "Confirm commercial operation, actual staffing, eligible capital placed in service and local fiscal outcomes after opening.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "dartpoints-columbus-expansion",
      "stable_id": "dartpoints-columbus-expansion",
      "aliases": [],
      "parent_id": null,
      "record_unit": "project",
      "current_name": "DartPoints — Columbus expansion",
      "former_names": [],
      "state": "IN",
      "city": "Columbus",
      "county": "Bartholomew",
      "owner": "DartPoints",
      "developer": null,
      "operator": "DartPoints",
      "utility": "Duke Energy Indiana",
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "unknown",
      "status_basis": "Expansion",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false,
        "note": "Operating CLU01 publishes 735 kW critical IT and 2.5 MW utility power; expansion demand remains unknown."
      },
      "sources": [
        {
          "title": "DartPoints facility page",
          "url": "https://dartpoints.com/locations/clu01-columbus-in/",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://dartpoints.com/locations/clu01-columbus-in/",
          "source_type": "company"
        }
      ],
      "confidence": "medium",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Columbus",
        "county": "Bartholomew",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "attributed",
      "evidence_tier": "operator-confirmed",
      "note": "DartPoints confirms an operating Columbus facility; its current facility page lists 735 kW critical IT load and 2.5 MW utility power. Expansion demand remains unknown.",
      "profile_url": null,
      "verified_fields": null,
      "announced_investment": null,
      "permanent_jobs": null,
      "power_detail": null,
      "cooling_water": null,
      "incentives_commitments": null,
      "next_check": null,
      "aggregate_exclude": false,
      "rights_class": "reference_only"
    },
    {
      "id": "digital-crossroads-hammond",
      "stable_id": "digital-crossroads-hammond",
      "aliases": [],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Digital Crossroad — Hammond campus",
      "former_names": [],
      "state": "IN",
      "city": "Hammond",
      "county": "Lake",
      "owner": "Digital Crossroad",
      "developer": null,
      "operator": "Digital Crossroad",
      "utility": "NIPSCO",
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "operating",
      "status_basis": "Partially operational; CoreWeave expansion agreement expired",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "City of Hammond development-agreement notice",
          "url": "https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Hammond",
        "county": "Lake",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "DX-1 operates at the campus. Hammond says the separate CoreWeave/Decennial development agreement expired June 30, 2026 after milestones were not met. Expansion demand remains unknown.",
      "profile_url": "/projects/coreweave-hammond/",
      "verified_fields": [
        "expansion-agreement expiration"
      ],
      "announced_investment": null,
      "permanent_jobs": null,
      "power_detail": null,
      "cooling_water": null,
      "incentives_commitments": null,
      "next_check": null,
      "aggregate_exclude": true,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "coreweave-hammond",
      "stable_id": "coreweave-hammond",
      "aliases": [],
      "parent_id": "digital-crossroads-hammond",
      "record_unit": "project",
      "current_name": "CoreWeave / Digital Crossroads expansion",
      "former_names": [],
      "state": "IN",
      "city": "Hammond",
      "county": "Lake",
      "owner": "Decennial Group / Digital Crossroads",
      "developer": "Decennial Group / Digital Crossroads",
      "operator": "CoreWeave",
      "utility": null,
      "iso": null,
      "acres": null,
      "lifecycle_status": "expired",
      "status_basis": "Hammond says the separate development agreement expired after required milestones were not satisfied by the June 30, 2026 deadline. The existing DX-1 facility remains operating.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Hammond development-agreement release",
          "url": "https://www.gohammond.com/hammond-approves-development-agreement-for-new-data-center/",
          "type": "municipal announcement",
          "published": "2025-06-10",
          "retrieved": "2026-09-11",
          "locator": "https://www.gohammond.com/hammond-approves-development-agreement-for-new-data-center/",
          "source_type": "government"
        },
        {
          "title": "Hammond Common Council minutes",
          "url": "https://www.gohammond.com/document_library/meeting_minutes_and_agendas/city_council/2025/06-09-25_minutes.pdf",
          "type": "municipal meeting record",
          "published": "2025-06-09",
          "retrieved": "2026-09-11",
          "locator": "https://www.gohammond.com/document_library/meeting_minutes_and_agendas/city_council/2025/06-09-25_minutes.pdf",
          "source_type": "government"
        },
        {
          "title": "Hammond agreement-expiration release",
          "url": "https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/",
          "type": "municipal outcome record",
          "published": "2026-07-01",
          "retrieved": "2026-09-11",
          "locator": "https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/",
          "source_type": "government"
        },
        {
          "title": "Digital Crossroad Indiana facility",
          "url": "https://digitalcrossroad.com/data-centers/indiana-data-center/",
          "type": "operator facility disclosure",
          "published": "current as reviewed 2026-09-10",
          "retrieved": "2026-09-11",
          "locator": "https://digitalcrossroad.com/data-centers/indiana-data-center/",
          "source_type": "company"
        }
      ],
      "confidence": "medium",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Hammond",
        "county": "Lake",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "Expansion agreement expired and expansion not delivered; existing facility operating",
      "note": "Expansion agreement expired and expansion not delivered; existing facility operating",
      "profile_url": "/projects/coreweave-hammond/",
      "verified_fields": null,
      "announced_investment": {
        "value": "multibillion-dollar",
        "kind": "city description; no precise amount established",
        "scope": "450,000-square-foot expansion"
      },
      "permanent_jobs": {
        "value": "35 to 90 positions paying more than $75,000",
        "kind": "city-council projection for proposed expansion",
        "observed": "not delivered; due status not established because the expansion agreement expired"
      },
      "power_detail": {
        "value": "180 MW",
        "kind": "city-reported project specification"
      },
      "cooling_water": {
        "value": "Not established in the reviewed city release.",
        "kind": "unknown"
      },
      "incentives_commitments": "The expired agreement referenced Community Impact Payments. No payment is treated as delivered without evidence that it came due and was paid.",
      "next_check": "Archive and extract the expired agreement, determine which milestones failed, and monitor any replacement development proposal separately from the operating DX-1 facility.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "microsoft-la-porte",
      "stable_id": "microsoft-la-porte",
      "aliases": [
        "microsoft-la-porte-1"
      ],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Microsoft — La Porte",
      "former_names": [],
      "state": "IN",
      "city": "La Porte",
      "county": "LaPorte",
      "owner": "Microsoft",
      "developer": "Microsoft",
      "operator": "Microsoft",
      "utility": "NIPSCO",
      "iso": "MISO",
      "acres": 489,
      "lifecycle_status": "construction",
      "status_basis": "Microsoft reported a June 2026 groundbreaking; operations have not been verified. Local incentive legal effect is limited to what the minutes record; the adopted resolution text was not obtained.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Microsoft Local announcement",
          "url": "https://local.microsoft.com/blog/microsoft-breaks-ground-on-la-porte-datacenter-project/",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://local.microsoft.com/blog/microsoft-breaks-ground-on-la-porte-datacenter-project/",
          "source_type": "company"
        },
        {
          "title": "IEDC project announcement",
          "url": "https://iedc.in.gov/events/news/details/2024/06/04/gov-holcomb-announces-plans-for-new-1b-microsoft-data-center-in-northwest-indiana",
          "type": "government announcement",
          "published": "2024-06-04",
          "retrieved": "2026-09-11",
          "locator": "https://iedc.in.gov/events/news/details/2024/06/04/gov-holcomb-announces-plans-for-new-1b-microsoft-data-center-in-northwest-indiana",
          "source_type": "government"
        },
        {
          "title": "La Porte Common Council minutes, March 2, 2026",
          "url": "https://www.cityoflaporte.com/uploads/minutes/m_1932_Council-Mar.2-2026-Minutes.docx",
          "type": "municipal meeting record",
          "published": "2026-03-02",
          "retrieved": "2026-09-11",
          "locator": "'Introduction of a Resolution ... Approving the Rescission of a Taxpayer Agreement, Including the Termination of Tax Abatement Authorized Therein' and 'Motion/Vote – Adopt Resolution R-3-2026' ('unanimously carried')",
          "source_type": "government"
        },
        {
          "title": "La Porte Common Council minutes, May 18, 2026",
          "url": "https://www.cityoflaporte.com/uploads/minutes/m_1937_Council-May.18-2026-Minutes.docx",
          "type": "municipal meeting record",
          "published": "2026-05-18",
          "retrieved": "2026-09-11",
          "locator": "'Introduction of a Framework Infrastructure Development Agreement with Microsoft'",
          "source_type": "government"
        },
        {
          "title": "IEDC Transparency Portal contract record, Microsoft Corporation (Project ID 425481, fund type DATA)",
          "url": "https://transparencyportal.iedc.in.gov/viewtaxgrantloancontract/210ab15f3de5ee11904d001dd8306d4e",
          "type": "state incentive record",
          "published": "current as reviewed 2026-09-11",
          "retrieved": "2026-09-11",
          "locator": "status 'Pending Accepted Offer'; expected qualified investment $2,980,000,000; expected new jobs by contract end 200; no agreement PDF posted",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "La Porte",
        "county": "LaPorte",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [
        {
          "date": "2026-09-11",
          "field": "record",
          "summary": "The Common Council minutes record 'Motion/Vote – Adopt Resolution R-3-2026' and say the motion was unanimously carried. The LEAP director states that the resolution refers to the taxpayer agreement approved in 2024 with Microsoft."
        }
      ],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "Microsoft reported a June 2026 groundbreaking. La Porte Common Council minutes (2 March 2026) show the council introduced and unanimously adopted Resolution R-3-2026, approving the rescission of the 2024 local Microsoft taxpayer agreement and termination of its tax abatement, and IEDC lists the state exemption as a pending offer with no executed agreement posted. Project demand and acreage remain unknown pending independent support.",
      "profile_url": null,
      "verified_fields": [
        "owner",
        "location",
        "groundbreaking"
      ],
      "announced_investment": {
        "value": "$1 billion",
        "kind": "government-reported company plan",
        "scope": "245,000-square-foot first announced campus"
      },
      "permanent_jobs": {
        "value": "2024 state announcement: up to 200 by end of 2032. June 2026 Microsoft update: more than 600 permanent Microsoft jobs in first phase.",
        "kind": "two announced claims with different scopes",
        "observed": "not yet reconciled"
      },
      "power_detail": {
        "value": "not established in the reviewed primary records",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "Microsoft says the campus will use closed-loop liquid cooling. Evaporation, source-water mix, permitted quantities and measured use are not established.",
        "kind": "company design claim + evidence gaps"
      },
      "incentives_commitments": "The 2 March 2026 council minutes record unanimous adoption of Resolution R-3-2026, whose agenda title describes rescission of the 2024 Microsoft taxpayer agreement, including termination of the tax abatement. DataCenterData has not obtained the adopted resolution text and therefore does not independently state its full legal effect. IEDC showed the state DATA exemption as a pending accepted offer when checked. June 2026 groundbreaking and the 600+ first-phase jobs statement remain company claims/projections, not observed outcomes.",
      "next_check": "Obtain the adopted text of Resolution R-3-2026 and the terms of the Framework Infrastructure Development Agreement; check whether the state exemption offer is executed; retrieve NIPSCO terms; determine whether the 200-job and 600-job statements reflect changed scope, phases or definitions before grading either claim.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "sabey-indianapolis",
      "stable_id": "sabey-indianapolis",
      "aliases": [],
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Sabey — Decatur Technology Park",
      "former_names": [],
      "state": "IN",
      "city": "Indianapolis",
      "county": "Marion",
      "owner": "Sabey Data Center Properties",
      "developer": null,
      "operator": "Sabey Data Center Properties",
      "utility": "AES Indiana",
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "approved",
      "status_basis": "Approved subject to commitments; construction not verified",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Indianapolis Metropolitan Development Commission hearing results, 18 March 2026",
          "url": "https://indianapolis-in.municodemeetings.com/sites/indianapolis-in.municodemeetings.com/files/fileattachments/mdc_hearing_examiner/meeting/5368/3-18-2026_hearing_results_-municode.pdf",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://indianapolis-in.municodemeetings.com/sites/indianapolis-in.municodemeetings.com/files/fileattachments/mdc_hearing_examiner/meeting/5368/3-18-2026_hearing_results_-municode.pdf",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure",
        "construction-start milestone"
      ],
      "location": {
        "city": "Indianapolis",
        "county": "Marion",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [
        {
          "date": "2026-09-11",
          "field": "record",
          "summary": "status was 'Approved; construction not verified' while the only linked source was the petitioner's appendix, which shows a request rather than a decision. The verification source is now the commission's hearing results. Prior verification_url: https://indianapolis-in.municodemeetings.com/sites/indianapolis-in.municodemeetings.com/files/fileattachments/mdc_hearing_examiner/meeting/5368/2025-cap-856_2025-cvr-856_petitioner_appendix_mdc_3-18-26_final.pdf; prior verified_fields: local filing, cooling claim, cost commitment."
        },
        {
          "date": "2026-09-12",
          "field": "lifecycle_status",
          "summary": "Changed from construction to approved. The commission record establishes approval subject to commitments, but no reviewed primary source establishes that construction began."
        }
      ],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "The commission approved the rezoning-commitment and variance petitions subject to commitments. The petition describes a closed-loop air-cooled system and a commitment to pay all related costs of a proposed substation and energy infrastructure. Project demand remains unknown pending independent support.",
      "profile_url": null,
      "verified_fields": [
        "approval subject to commitments",
        "proposed cooling commitment",
        "proposed energy-cost commitment"
      ],
      "announced_investment": null,
      "permanent_jobs": null,
      "power_detail": null,
      "cooling_water": null,
      "incentives_commitments": null,
      "next_check": null,
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "aws-new-carlisle",
      "stable_id": "aws-new-carlisle",
      "aliases": [],
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "AWS — New Carlisle",
      "former_names": [],
      "state": "IN",
      "city": "New Carlisle",
      "county": null,
      "owner": "Amazon Web Services",
      "developer": "Amazon Web Services",
      "operator": "Amazon Web Services; New Carlisle is one site in the multi-site Project Rainier cluster",
      "utility": "Indiana Michigan Power",
      "iso": "PJM",
      "acres": null,
      "lifecycle_status": "expanding",
      "status_basis": "Amazon says the multi-site Project Rainier compute cluster is operational and identifies New Carlisle as one site; this does not establish completion of the entire New Carlisle campus buildout.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Amazon newsroom announcement",
          "url": "https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster",
          "type": "primary",
          "published": null,
          "retrieved": "2026-09-11",
          "locator": "https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster",
          "source_type": "company"
        },
        {
          "title": "IEDC project announcement",
          "url": "https://iedc.in.gov/events/news/details/2024/04/25/gov.-holcomb-announces-amazon-web-services-plans-to-invest-11b-to-create-a-new-data-center-campus-in-northern-indiana",
          "type": "government announcement",
          "published": "2024-04-25",
          "retrieved": "2026-09-11",
          "locator": "https://iedc.in.gov/events/news/details/2024/04/25/gov.-holcomb-announces-amazon-web-services-plans-to-invest-11b-to-create-a-new-data-center-campus-in-northern-indiana",
          "source_type": "government"
        },
        {
          "title": "AWS economic-development manager operating account",
          "url": "https://www.sbrchamber.com/news/2026/07/09/default/amazon-s-investment-is-building-lasting-opportunity-for-st.-joseph-county/",
          "type": "AWS-authored opinion",
          "published": "2026-07-09",
          "retrieved": "2026-09-11",
          "locator": "https://www.sbrchamber.com/news/2026/07/09/default/amazon-s-investment-is-building-lasting-opportunity-for-st.-joseph-county/",
          "source_type": "company"
        },
        {
          "title": "AWS project page",
          "url": "https://www.sbrchamber.com/pages/aws-economic/",
          "type": "chamber-published project summary",
          "published": "current as reviewed 2026-09-10",
          "retrieved": "2026-09-11",
          "locator": "https://www.sbrchamber.com/pages/aws-economic/",
          "source_type": "company"
        },
        {
          "title": "IEDC Project 424567 — DATA contract detail",
          "url": "https://transparencyportal.iedc.in.gov/viewtaxgrantloancontract/8c0f68149feaee11904d001dd8306d4e",
          "type": "government incentive portal",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Incentive Details and Project Performance Details; Project ID 424567; DATA status Executed",
          "source_type": "government"
        },
        {
          "title": "IEDC DATA Center Tax Exemption Agreement — Project 424567",
          "url": "https://transparencyportal.iedc.in.gov/iedc-transparency-api/api/contract/8c0f68149feaee11904d001dd8306d4e/pdf",
          "type": "executed government agreement",
          "published": "2024-11-08",
          "retrieved": "2026-09-12",
          "locator": "PDF p. 1 sections 3.C and 3.E; p. 2 sections 6.C–D; p. 13 Exhibit A section 2.A–B; p. 15 Exhibit B",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "New Carlisle",
        "county": null,
        "address": null,
        "precision": "place_centroid",
        "note": "St. Joseph"
      },
      "history": [
        {
          "date": "2026-09-12",
          "field": "incentives_commitments",
          "summary": "IEDC Project 424567 portal instruments and the DATA agreement were independently retrieved and separated by program, status, field name and contractual condition.",
          "from": "The 2024 announcement package terms without a retrieved contract split.",
          "to": "Attributed HBI, EDGE, RTC, SEF and DATA portal statuses plus qualified DATA agreement conditions; no inferred benefit or project outcome.",
          "reason": "Primary-record follow-up established the instrument split while preserving uncertainty around paid/certified and performance fields.",
          "evidence_url": "https://transparencyportal.iedc.in.gov/viewtaxgrantloancontract/8c0f68149feaee11904d001dd8306d4e"
        },
        {
          "date": "2026-09-11",
          "field": "permanent_jobs",
          "summary": "status was 'supported-as-delivered' with value 'At least 1,000 baseline; 1,056 full-time AWS employees later reported'. The company-linked counts sit on either side of the baseline, so the reviewed record does not support a delivery conclusion.",
          "from": "supported-as-delivered / At least 1,000 baseline; 1,056 full-time AWS employees later reported",
          "to": "Company claim: AWS says nearly 1,000 hired; an undated Chamber page says 1,056. Not independently observed.",
          "reason": "Jobs delivery label was stronger than the company-linked record.",
          "evidence_url": "https://www.sbrchamber.com/news/2026/07/09/default/amazon-s-investment-is-building-lasting-opportunity-for-st.-joseph-county/"
        }
      ],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed",
      "note": "Amazon says the multi-site Project Rainier cluster is operational and New Carlisle is one site. That does not prove completion of the full campus. Project demand and acreage remain unknown pending independent support.",
      "profile_url": "/projects/aws-new-carlisle/",
      "verified_fields": [
        "operator",
        "site relationship",
        "operating milestone"
      ],
      "announced_investment": {
        "value": "$11 billion",
        "kind": "government-reported company baseline",
        "scope": "original New Carlisle campus",
        "reported_outcome": "$13.8 billion reported by AWS-linked 2026 accounts; eligible-capital and placed-in-service scope not independently reconciled"
      },
      "permanent_jobs": {
        "value": "at least 1,000",
        "kind": "announced baseline",
        "observed": "AWS-linked 2026 reporting says nearly 1,000 operations staff; the Chamber project page says 1,056 full-time AWS employees. Project-specific CF-1 and payroll definitions are not yet reconciled."
      },
      "power_detail": {
        "value": "not stated in the reviewed state agreement summary",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "An AWS-authored 2026 account says outside air is used about 98% of the year and estimates approximately 18 million gallons annually at full buildout. This is not current metered use, a permit quantity or a potable-water figure.",
        "kind": "company design and projection + evidence gap"
      },
      "incentives_commitments": "Up to $98.3 million across four listed programs: HBI $55 million Executed, EDGE $18.3 million Executed, RTC $20 million in Post Term Reporting Period, and SEF $5 million Pending Accepted Offer in IEDC Project 424567 on 12 September 2026. The separate DATA exemption agreement lists an $800 million minimum qualified investment, an $11 billion extension test, and a maximum 2073 exemption deadline, with IEDC discretion under section 6.D to deny, suspend, or extend the exemption if the $11 billion extension test is missed. Portal Paid/Certified fields and contract terms are not treated as cash paid, benefits earned, jobs observed, or completed investment.",
      "next_check": "Reconcile investment placed in service, observed employment, local tax flows, water permits and utility cost allocation.",
      "aggregate_exclude": false,
      "rights_class": "reference_only",
      "rights_migration": {
        "previous_class": "licensed_core",
        "reason": "Legacy source-class inference was not an independently approved field-level reuse decision."
      }
    },
    {
      "id": "dcblox-indianapolis",
      "stable_id": "dcblox-indianapolis",
      "aliases": [],
      "parent_id": null,
      "record_unit": "project",
      "current_name": "DC BLOX Thunderbird",
      "former_names": [],
      "state": "IN",
      "city": "Indianapolis",
      "county": "Marion",
      "owner": "DC BLOX",
      "developer": "DC BLOX",
      "operator": "DC BLOX; phase-two use not defined",
      "utility": null,
      "iso": null,
      "acres": null,
      "lifecycle_status": "construction",
      "status_basis": "The Metropolitan Development Commission's July 15, 2026 hearing results record 'Approved' for 2026-CVR-815 (Amended) and 2026-CPL-815 (305 Fintail Drive; DCB Indianapolis, LLC), with a footnote citing the MDC rule that no petition is considered finally approved until the required commitments are filed. Local reporting says neighbors and others petitioned for judicial review on August 14, 2026; the court record was not reviewed. The developer page still describes evaluation/permitting; construction is not treated as started.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Thunderbird project page and submitted documents",
          "url": "https://www.dcblox.com/indianapolisdatacenter/",
          "type": "developer project disclosure",
          "published": "current as reviewed 2026-09-10",
          "retrieved": "2026-09-11",
          "locator": "https://www.dcblox.com/indianapolisdatacenter/",
          "source_type": "unknown"
        },
        {
          "title": "East side data center wins approval",
          "url": "https://www.wfyi.org/wfyi-news/2026-07-15/east-side-data-center-wins-approval-despite-community-opposition",
          "type": "independent local reporting",
          "published": "2026-07-15",
          "retrieved": "2026-09-11",
          "locator": "https://www.wfyi.org/wfyi-news/2026-07-15/east-side-data-center-wins-approval-despite-community-opposition",
          "source_type": "news"
        },
        {
          "title": "Metropolitan Development Commission hearing results, July 15, 2026",
          "url": "https://indianapolis-in.municodemeetings.com/sites/indianapolis-in.municodemeetings.com/files/fileattachments/mdc_hearing_examiner/meeting/5458/7-15-2026_mdc_hearing_results_-_municode.pdf",
          "type": "municipal decision record",
          "published": "2026-07-15",
          "retrieved": "2026-09-11",
          "locator": "2026-CVR-815 (Amended) / 2026-CPL-815 entry and footnote 1 (MDC Rules of Procedure Article VIII.5.A)",
          "source_type": "government"
        },
        {
          "title": "Judicial review petition report",
          "url": "https://mirrorindy.org/dc-blox-data-center-irvington-east-side-indianapolis-judicial-review/",
          "type": "independent local reporting",
          "published": "2026-08-21",
          "retrieved": "2026-09-11",
          "locator": "https://mirrorindy.org/dc-blox-data-center-irvington-east-side-indianapolis-judicial-review/",
          "source_type": "news"
        }
      ],
      "confidence": "medium",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Indianapolis",
        "county": "Marion",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "attributed",
      "evidence_tier": "Conditional local approval recorded; judicial review reported",
      "note": "Conditional local approval recorded; judicial review reported",
      "profile_url": null,
      "verified_fields": null,
      "announced_investment": {
        "value": "$1.8–$2.0 billion",
        "kind": "developer estimate",
        "scope": "two buildings across two phases"
      },
      "permanent_jobs": {
        "value": "small on-site team; number not disclosed",
        "kind": "developer description",
        "observed": "not applicable"
      },
      "power_detail": {
        "value": "revised critical IT load not stated; developer says it reduced the design by 28 MW",
        "kind": "company design update"
      },
      "cooling_water": {
        "value": "Developer claims closed-loop cooling and water use comparable to a commercial building; no permit or measured quantity has been reconciled.",
        "kind": "company claim"
      },
      "incentives_commitments": "Publicly submitted statement of commitments is linked by the developer; local approval and enforceable terms require independent extraction.",
      "next_check": "Verify local disposition, extract the filed commitments and air/water documents, and separate peak construction jobs from permanent staffing.",
      "aggregate_exclude": false,
      "rights_class": "reference_only"
    },
    {
      "id": "amazon-hobart",
      "stable_id": "amazon-hobart",
      "aliases": [],
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Amazon Data Services — Hobart project",
      "former_names": [],
      "state": "IN",
      "city": "Hobart",
      "county": "Lake",
      "owner": "Amazon Data Services, Inc.",
      "developer": "Amazon Data Services, Inc.",
      "operator": "Amazon Data Services, Inc.",
      "utility": null,
      "iso": null,
      "acres": null,
      "lifecycle_status": "approved",
      "status_basis": "City archives list 2026 tax-abatement and enterprise-IT exemption agreements and a 2025 sewer-service process. In a July 2026 application to IDEM, Amazon Data Services, Inc. proposes two data-center sites in Hobart, SBN520 at 4751 E. 61st Avenue (six buildings) and SBN750 at 6197 Colorado St. (20 buildings); an application is not an issued permit. The IURC approved a NIPSCO special contract with Amazon Data Services, Inc. for northern Indiana data-center load on 17 June 2026; the order does not name Hobart.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Hobart City Council resolution archive",
          "url": "https://www.cityofhobart.org/Archive/37",
          "type": "municipal record index",
          "published": "2025–2026",
          "retrieved": "2026-09-11",
          "locator": "https://www.cityofhobart.org/Archive/37",
          "source_type": "government"
        },
        {
          "title": "Hobart Sanitary District agenda",
          "url": "https://www.cityofhobart.org/AgendaCenter/ViewFile/Agenda/_12302025-2500",
          "type": "municipal agenda",
          "published": "2025-12-30",
          "retrieved": "2026-09-11",
          "locator": "https://www.cityofhobart.org/AgendaCenter/ViewFile/Agenda/_12302025-2500",
          "source_type": "government"
        },
        {
          "title": "Hobart Resolution 2026-02 and real-property abatement agreement",
          "url": "https://cityofhobart.org/Archive.aspx?ADID=1323",
          "type": "executed municipal agreement package",
          "published": "2026",
          "retrieved": "2026-09-12",
          "locator": "PDF pp. 1, 5-8 and agreement §§2.B-2.I: approval, nonbinding estimates, ten-year building abatement, annual reporting and community payments",
          "source_type": "agreement"
        },
        {
          "title": "Hobart Resolution 2026-03 and community enhancement agreement",
          "url": "https://cityofhobart.org/Archive.aspx?ADID=1324",
          "type": "executed municipal agreement package",
          "published": "2026",
          "retrieved": "2026-09-12",
          "locator": "PDF pp. 13-17: nonbinding estimates, annual May 14 reporting, annual building payment, $5 million trigger and remedies",
          "source_type": "agreement"
        },
        {
          "title": "Hobart Resolution 2026-04 and enterprise IT exemption agreement",
          "url": "https://cityofhobart.org/Archive.aspx?ADID=1325",
          "type": "executed municipal agreement package",
          "published": "2026",
          "retrieved": "2026-09-12",
          "locator": "PDF pp. 7-9 and Exhibit B: 35-year exemption, wage condition, reporting, annual IT payment and water/sewer cooperation",
          "source_type": "agreement"
        },
        {
          "title": "Application for New Source Minor PSD/EO construction approval and FESOP, Site SBN520/750 (prepared by Ramboll for Amazon Data Services, Inc.)",
          "url": "https://ecm.idem.in.gov/cs/idcplg?IdcService=GET_FILE&dDocName=83997206&RevisionSelectionMethod=LatestReleased&Rendition=web&allowInterrupt=1",
          "type": "air permit application, not an issued permit",
          "published": "2026-07-24",
          "retrieved": "2026-09-11",
          "locator": "cover letter and project description (SBN520 4751 E. 61st Avenue; SBN750 6197 Colorado St.; six and twenty data center buildings); GSD-13 adjacent landowner list",
          "source_type": "permit"
        },
        {
          "title": "Order, Cause No. 46322 (NIPSCO special contract with Amazon Data Services, Inc.)",
          "url": "https://secure.in.gov/iurc/files/ord_46322_061726.pdf",
          "type": "utility regulatory order",
          "published": "2026-06-17",
          "retrieved": "2026-09-11",
          "locator": "relief requested and findings: Special Contract dated September 18, 2025 between NIPSCO and Amazon Data Services, Inc.",
          "source_type": "docket"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "independently supported demand figure"
      ],
      "location": {
        "city": "Hobart",
        "county": "Lake",
        "address": null,
        "precision": "place_centroid",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "Primary-reviewed parent project. Two proposed permit-site children are tracked separately and excluded from parent-level counts.",
      "note": "Hobart approved local agreements for Amazon Data Services, Inc.; IDEM's application describes two proposed sites. The agreements explicitly do not compel construction, investment or jobs, so approval is not described as construction.",
      "profile_url": null,
      "verified_fields": [
        "legal entity",
        "local agreement approvals",
        "two proposed site addresses",
        "agreement terms"
      ],
      "announced_investment": {
        "value": "potentially more than $11 billion",
        "kind": "nonbinding company estimate in executed city agreements",
        "scope": "full Hobart project"
      },
      "permanent_jobs": {
        "value": "more than 400 company positions at full development; estimated $37.44 hourly wage",
        "kind": "nonbinding company estimate in executed city agreements",
        "observed": "not verified"
      },
      "power_detail": {
        "value": "not established in the reviewed city index",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "A sewer-service agreement is referenced; cooling architecture and consumption are not established.",
        "kind": "unknown"
      },
      "incentives_commitments": "Executed agreements provide a ten-year 100% real-property abatement per qualifying building, with no certificate of occupancy after 2034-01-01 qualifying; an annual building payment capped at the lesser of $500,000 or the abatement; a one-time $5 million payment triggered by the first building permit and city invoice; a 35-year 100% qualified enterprise-IT exemption per building; and an annual IT payment capped at the lesser of $1.5 million or avoided tax. All payments remain contractually committed with triggers and delivery unverified.",
      "next_check": "Verify first building permit and $5 million invoice/payment; issued IDEM permits; annual May 14 compliance reports; actual investment, employment and community payments. Do not allocate the NIPSCO cluster load to Hobart without site-level evidence.",
      "aggregate_exclude": false,
      "rights_class": "reference_only"
    },
    {
      "id": "amazon-nipsco-northern-indiana-service",
      "stable_id": "amazon-nipsco-northern-indiana-service",
      "aliases": [],
      "parent_id": null,
      "record_unit": "project",
      "generate_page": true,
      "counting_unit": "contract_ledger",
      "current_name": "Amazon / NIPSCO northern Indiana service program",
      "former_names": [],
      "state": "IN",
      "city": null,
      "county": null,
      "owner": null,
      "developer": "Amazon Data Services, Inc.",
      "operator": null,
      "utility": "NIPSCO",
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "approved",
      "status_basis": "The IURC approved NIPSCO's special contract with Amazon Data Services on June 17, 2026. Service commencement by January 1, 2027 and ramp to full load by the end of 2032 are contractual milestones not yet due, not observed outcomes.",
      "capacity": {
        "value": 2400,
        "unit": "MW",
        "kind": "utility_service",
        "scope": "full_buildout",
        "aggregation_allowed": false,
        "note": "Contracted northern Indiana multi-site load at full ramp; allocation among individual Amazon sites is confidential/unknown and this is not IT capacity or current demand."
      },
      "sources": [
        {
          "title": "IURC final order, Cause No. 46322",
          "url": "https://secure.in.gov/iurc/files/ord_46322_061726.pdf",
          "type": "utility regulatory order",
          "published": "2026-06-17",
          "retrieved": "2026-09-12",
          "locator": "PDF pp. 2-5, 32-38, 53-57: term, load ramp, generation and credit projections, cost allocation limits, studies and annual reporting",
          "source_type": "docket"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "site-level allocation",
        "actual demand",
        "actual generation",
        "actual customer credits",
        "site tied to confidential water agreement"
      ],
      "location": {
        "city": null,
        "county": null,
        "address": null,
        "precision": "unknown",
        "note": "The order concerns multiple northern Indiana facilities and does not publicly allocate load to named sites."
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed cluster-level contract",
      "note": "This is a contract/program ledger, not an additional physical campus. It exists to prevent 2,400 MW, 3,000 MW generation and water-agreement facts from being misassigned to Hobart, New Carlisle or Wheatfield.",
      "profile_url": null,
      "verified_fields": [
        "contract approval",
        "cluster load ceiling",
        "term and reporting duties"
      ],
      "announced_investment": {
        "value": "not established",
        "kind": "unknown",
        "scope": "multi-site program"
      },
      "permanent_jobs": {
        "value": "not established",
        "kind": "unknown",
        "observed": "not established"
      },
      "power_detail": {
        "value": "Up to 2,400 MW Amazon load by end-2032; 3,000 MW planned generation; projected $1.1B customer credits and approximately $7/month residential credit at full ramp",
        "kind": "approved contract terms and regulatory projections, not observed outcomes"
      },
      "cooling_water": {
        "value": "The order references a confidential-site water agreement but does not establish which facility, quantity or cooling architecture.",
        "kind": "unknown"
      },
      "incentives_commitments": "Amazon bears customer-specific and specified MISO costs. The order permits NIPSCO to seek later allocation of transmission costs to other customers if it proves shared benefits in a future docket; therefore zero ratepayer risk is not established.",
      "next_check": "Annual actual-versus-forecast demand/capacity filing; service start by 2027-01-01; transmission-study dockets; full-ramp projection at year-end 2032.",
      "aggregate_exclude": true,
      "rights_class": "reference_only"
    },
    {
      "id": "project-louie-mooresville",
      "stable_id": "project-louie-mooresville",
      "aliases": [
        "Project Louie",
        "Google Project Louie"
      ],
      "parent_id": null,
      "record_unit": "campus",
      "generate_page": true,
      "current_name": "Project Louie — Woodland Caribou LLC (Google-associated)",
      "former_names": [],
      "state": "IN",
      "city": "Mooresville",
      "county": "Morgan",
      "owner": null,
      "developer": "Woodland Caribou LLC (permit applicant)",
      "operator": null,
      "utility": "AES Indiana",
      "iso": "MISO",
      "acres": 469,
      "lifecycle_status": "proposed",
      "status_basis": "An IDEM Section 401 application/public notice describes a phased six-building data-center campus. This is environmental permitting, not proof that construction began.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "IDEM Section 401 application and public notice — Project Louie",
          "url": "https://www.in.gov/idem/files/notice_20260223_401_wqc001428.pdf",
          "type": "state environmental permit application/public notice",
          "published": "2026-02-23",
          "retrieved": "2026-09-12",
          "locator": "PDF p. 1 and application §4.4: Woodland Caribou applicant, 1598 W State Road 42, six buildings, 469 acres, stream and wetland impacts",
          "source_type": "permit"
        },
        {
          "title": "Morgan County recorded survey — Project Louie, Google",
          "url": "https://morgancounty.in.gov/files/Surveyor/Records%20and%20Resources/INDIVIDUAL%20RECORDED%20SURVEYS/T13N%20R1E/S5%2C%206%20T13N%20R1E%20%26%20S1%20T13N%20R1W%20PROJECT%20LOUIE%2C%20GOOGLE.pdf",
          "type": "county survey record",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Official county filename associates Project Louie and Google; it does not establish subsidiary ownership or operator identity",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "final utility order",
        "legal relationship among Google and Woodland Caribou",
        "construction start",
        "operational power, cooling and water"
      ],
      "location": {
        "city": "Mooresville",
        "county": "Morgan",
        "address": "1598 W State Road 42, Mooresville, IN",
        "precision": "exact",
        "note": "Approximate campus center 39.592896, -86.460713; address and bounds from permit application."
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed environmental-permitting record",
      "note": "The notice reports 627 linear feet of stream impact while the application reports 691 feet; both report 0.05 acre of wetland impact. The discrepancy is preserved.",
      "profile_url": null,
      "verified_fields": [
        "applicant",
        "location",
        "six-building scope",
        "environmental-permitting status"
      ],
      "announced_investment": {
        "value": "$1.3 billion of infrastructure and $770 million projected customer savings",
        "kind": "AES utility projections/claims",
        "scope": "proposal; final order not obtained"
      },
      "permanent_jobs": {
        "value": "not established",
        "kind": "unknown",
        "observed": "not established"
      },
      "power_detail": {
        "value": "Final approved contract terms not obtained",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "Section 401 impacts do not establish operational water use or cooling architecture.",
        "kind": "unknown"
      },
      "incentives_commitments": "Not established in reviewed sources.",
      "next_check": "Retrieve final IURC Cause 46394 order and confirm construction commencement, entity relationships and any utility cost protections.",
      "aggregate_exclude": false,
      "rights_class": "reference_only"
    },
    {
      "id": "amazon-hobart-sbn520",
      "stable_id": "amazon-hobart-sbn520",
      "aliases": [
        "SBN520"
      ],
      "parent_id": "amazon-hobart",
      "record_unit": "project",
      "generate_page": true,
      "current_name": "Amazon Hobart — SBN520",
      "former_names": [],
      "state": "IN",
      "city": "Hobart",
      "county": "Lake",
      "owner": "Amazon Data Services, Inc.",
      "developer": "Amazon Data Services, Inc.",
      "operator": null,
      "utility": null,
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "proposed",
      "status_basis": "IDEM received an air-permit application describing six proposed data-center buildings. An application is not an issued permit or construction milestone.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Amazon Hobart SBN520/750 air-permit application",
          "url": "https://ecm.idem.in.gov/cs/idcplg?IdcService=GET_FILE&dDocName=83997206&RevisionSelectionMethod=LatestReleased&Rendition=web&allowInterrupt=1",
          "type": "air-permit application",
          "published": "2026-07-24",
          "retrieved": "2026-09-12",
          "locator": "Cover and project description: SBN520, 4751 E. 61st Avenue, six proposed buildings",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "issued permit",
        "construction start",
        "capacity",
        "cooling and water"
      ],
      "location": {
        "city": "Hobart",
        "county": "Lake",
        "address": "4751 E. 61st Avenue, Hobart, IN",
        "precision": "exact",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed child site",
      "note": "Child of the Hobart parent project; excluded from parent-level counts.",
      "profile_url": null,
      "verified_fields": [
        "proposed site address",
        "six-building scope"
      ],
      "announced_investment": {
        "value": "not allocated from parent",
        "kind": "unknown",
        "scope": "site"
      },
      "permanent_jobs": {
        "value": "not allocated from parent",
        "kind": "unknown",
        "observed": "not established"
      },
      "power_detail": {
        "value": "not allocated from NIPSCO cluster",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "unknown",
        "kind": "unknown"
      },
      "incentives_commitments": "Parent-level agreements; site allocation not established.",
      "next_check": "Issued IDEM permit and construction milestone.",
      "aggregate_exclude": true,
      "rights_class": "reference_only"
    },
    {
      "id": "amazon-hobart-sbn750",
      "stable_id": "amazon-hobart-sbn750",
      "aliases": [
        "SBN750"
      ],
      "parent_id": "amazon-hobart",
      "record_unit": "project",
      "generate_page": true,
      "current_name": "Amazon Hobart — SBN750",
      "former_names": [],
      "state": "IN",
      "city": "Hobart",
      "county": "Lake",
      "owner": "Amazon Data Services, Inc.",
      "developer": "Amazon Data Services, Inc.",
      "operator": null,
      "utility": null,
      "iso": "MISO",
      "acres": null,
      "lifecycle_status": "proposed",
      "status_basis": "IDEM received an air-permit application describing twenty proposed data-center buildings. An application is not an issued permit or construction milestone.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "sources": [
        {
          "title": "Amazon Hobart SBN520/750 air-permit application",
          "url": "https://ecm.idem.in.gov/cs/idcplg?IdcService=GET_FILE&dDocName=83997206&RevisionSelectionMethod=LatestReleased&Rendition=web&allowInterrupt=1",
          "type": "air-permit application",
          "published": "2026-07-24",
          "retrieved": "2026-09-12",
          "locator": "Cover and project description: SBN750, 6197 Colorado Street, twenty proposed buildings",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "issued permit",
        "construction start",
        "capacity",
        "cooling and water"
      ],
      "location": {
        "city": "Hobart",
        "county": "Lake",
        "address": "6197 Colorado Street, Hobart, IN",
        "precision": "exact",
        "note": null
      },
      "history": [],
      "inventory_layer": "verified",
      "evidence_tier": "primary-reviewed child site",
      "note": "Child of the Hobart parent project; excluded from parent-level counts.",
      "profile_url": null,
      "verified_fields": [
        "proposed site address",
        "twenty-building scope"
      ],
      "announced_investment": {
        "value": "not allocated from parent",
        "kind": "unknown",
        "scope": "site"
      },
      "permanent_jobs": {
        "value": "not allocated from parent",
        "kind": "unknown",
        "observed": "not established"
      },
      "power_detail": {
        "value": "not allocated from NIPSCO cluster",
        "kind": "unknown"
      },
      "cooling_water": {
        "value": "unknown",
        "kind": "unknown"
      },
      "incentives_commitments": "Parent-level agreements; site allocation not established.",
      "next_check": "Issued IDEM permit and construction milestone.",
      "aggregate_exclude": true,
      "rights_class": "reference_only"
    }
  ],
  "candidate_queue": [
    {
      "name": "Vantage IN11",
      "place": "Pittsboro",
      "reason": "Local public-hearing record located; approvals, site scope and current status still need reconciliation."
    },
    {
      "name": "Takanock Goshen",
      "place": "Goshen / Elkhart County",
      "reason": "Third-party lead only; no project-level primary record accepted yet."
    },
    {
      "name": "Prologis Shelbyville",
      "place": "Shelbyville / Shelby County",
      "reason": "Third-party lead only; developer, tenant and local approval chain need confirmation."
    },
    {
      "name": "Sentinel Hebron",
      "place": "Hebron / Lake County",
      "reason": "Third-party lead only; project identity and status need primary confirmation."
    },
    {
      "name": "New Haven project",
      "place": "New Haven / Allen County",
      "reason": "Third-party lead only; owner, status and utility relationship unresolved."
    },
    {
      "name": "Brazil project",
      "place": "Brazil / Clay County",
      "reason": "Third-party lead only; owner, approvals and project scope unresolved."
    },
    {
      "name": "Metrobloks Martindale-Brightwood",
      "place": "Indianapolis / Marion County",
      "reason": "Local approval reported; primary case file, exact scope and pending litigation need reconciliation."
    },
    {
      "name": "AWS Wheatfield",
      "place": "Wheatfield / Jasper County",
      "reason": "County records and reporting located; owner, project scope, approval state and utility relationship need normalization."
    }
  ],
  "third_party_discovery": [
    {
      "source": "Cleanview",
      "reported_count": 157,
      "unit_note": "Page mixes operating and planned projects and exposes building-level records.",
      "url": "https://cleanview.co/data-centers/indiana"
    },
    {
      "source": "Baxtel",
      "reported_count": 135,
      "unit_note": "Commercial market page calls these facilities and separately enumerates provider sites.",
      "url": "https://baxtel.com/data-center/indiana"
    },
    {
      "source": "DataCenterMap",
      "reported_count": 125,
      "unit_note": "Commercial directory lists data centers across 13 Indiana markets.",
      "url": "https://www.datacentermap.com/usa/indiana/"
    }
  ],
  "publication": {
    "state": "IN",
    "state_name": "Indiana",
    "slug": "indiana",
    "kind": "projects",
    "record_key": "projects",
    "license": null,
    "reuse_scope": "reference only unless a record is explicitly rights-cleared",
    "rights_manifest": "/data/rights-manifest.json"
  },
  "third_party_discovery_rights_class": "reference_only"
}